Guides running a Business Impact Analysis, deriving RTO/RPO/MTPD, and structuring a business continuity plan aligned to ISO 22301. Use when the user asks to write a BCP, perform a BIA, set recovery objectives, align with ISO 22301, or plan continuity for a cyber outage.

Business continuity

Continuity is a business deliverable, not an IT one. You decide which activities must survive, how fast, and how much data they can lose; then IT/DR (load_skill disaster-recovery) builds to those numbers. Anchor on ISO 22301:2019 (BIA is clause 8.2.2); the 2024 Amd 1 adds climate considerations. verify: https://www.iso.org/standard/75106.html

Business Impact Analysis (the BIA method)

Work activity-by-activity (a process/service, not a server). For each:

  1. Criticality: what breaks if it stops? Score impact over time (1h / 24h / 1wk / 1mo) across axes: revenue, legal/regulatory, safety, contractual SLA, reputation. Impact almost always grows non-linearly with outage duration.
  2. MTPD (Maximum Tolerable Period of Disruption): the outage length after which the organisation's viability is irrevocably threatened. This is a business survival limit, set by the business, not negotiable down by IT convenience.
  3. Dependencies: map upstream/downstream (apps, data, people/skills, facilities, suppliers, utilities). A process is only as recoverable as its slowest dependency; surface single points of failure here. A 1h-RTO app on a 3rd party with a 24h SLA is a lie; fix the dependency or relax the RTO.
  4. Minimum resources: the floor of staff, systems, and data needed to run at a degraded-but-acceptable level (the MBCO, Minimum Business Continuity Objective).

Output: a prioritised list of critical activities with their MTPD, dependencies, and resource floor. Everything downstream derives from this; don't skip to solutions.

Deriving RTO and RPO

Nested constraint: RPO ≤ data-loss tolerance and RTO < MTPD (always leave a buffer; RTO == MTPD has zero margin and will breach).

  • RTO (Recovery Time Objective): target time to restore the activity. Derive it below MTPD with contingency for detection + decision + actual recovery, not just the restore step.
  • RPO (Recovery Point Objective): max acceptable data loss, in time. RPO directly sets backup/replication frequency: RPO 4h ⇒ you must capture state ≥ every 4h. RPO near-zero ⇒ synchronous replication (expensive; justify it from the BIA).
  • Sanity check: every RTO/RPO has a cost. If everything is "Tier 0, RTO 0", the BIA wasn't done: force the business to rank, because the budget will.

BCP structure (what the plan contains)

  • Scope & roles: activation authority, BC team, deputies (no single points).
  • Per-activity recovery plan: RTO/RPO, the workaround (manual/degraded mode to hit MBCO while systems recover), dependencies, and the restore procedure.
  • Resource & contact directory: staff, suppliers, sites, alternate-site arrangements. Keep an offline copy: a continuity plan only readable on the down system is useless.
  • Communications plan: internal cadence + external/stakeholder messaging (the crisis layer: load_skill crisis-management).
  • Maintenance: review on change and at least annually; exercise the plan (DR test types in disaster-recovery).

ISO 22301 alignment (PDCA, clauses 4 to 10)

  • Cl. 4 context & scope · Cl. 5 leadership + policy · Cl. 6 objectives · Cl. 7 resources/competence.
  • Cl. 8 operation, the engine: 8.2 BIA + risk assessment, 8.3 strategy selection, 8.4 procedures (BCP), 8.5 exercise programme.
  • Cl. 9 performance evaluation (metrics, internal audit, management review) · Cl. 10 improvement (corrective action). It's a PDCA management system; certification needs evidence of the loop turning, not a binder on a shelf.

Ransomware lens

  • Treat ransomware as a continuity event, not just a security one: assume primary systems AND online backups are simultaneously unavailable. Your RTO/RPO must hold when recovery starts from clean, offline copies (load_skill backup-recovery); re-derive RTO including rebuild-from-bare-metal + integrity-verification time, which dwarfs a routine restore.
  • BIA feeds the risk register: push critical-activity SPOFs into load_skill risk-assessment.
slack-gif-creatoranthropics/skillsKnowledge and utilities for creating animated GIFs optimized for Slack. Provides constraints, validation tools, and animation concepts. Use when users request animated GIFs for Slack like "make me a GIF of X doing Y for Slack."Stars: 198kUpdated Claude CodeCodexVerifiedInstall
ponytailDietrichGebert/ponytailLazy senior dev mode for any coding task: the smallest change that fully solves it, and a reply a busy human understands in one read.Stars: 196kUpdated Claude CodeCodexVerifiedInstall
ponytail-debtDietrichGebert/ponytailHarvest every shortcut: comment into one debt ledger, so deferrals get tracked instead of forgotten. One-shot report.Stars: 196kUpdated Claude CodeCodexVerifiedInstall
ponytail-debtDietrichGebert/ponytailList every `shortcut:` comment (and older `ponytail:` ones) as a debt ledger. One-shot report, changes nothing. Use for "ponytail debt", "what did ponytail defer", "list the shortcuts", /ponytail-debt.Stars: 196kUpdated Claude CodeCodexVerifiedInstall