This skill should be used when the user shares construction documents (DD set, 50%/100% CD, GMP set) and wants them reviewed through a constructor's lens — sequencing, tolerance stack-ups, MEP coordination, install access, lay-down logistics, temporary works, long-lead procurement, and phased operations. Trigger on 'constructability review', 'CM review', 'sequencing check', 'install access', 'crane reach', 'lay-down', 'long-lead', 'MEP coordination clearance', 'site logistics', or pasted CD context with build-feasibility intent. Generates a structured review markdown in `docs/constructability/` and appends to the project constructability index.

references/long_lead_items_2026.md

View on GitHub
# Long-Lead Items — Sourcing Methodology (NA)

This is **not** a lookup table. It is a methodology for building a project-specific long-lead register against current, vendor-quoted lead times.

---

## Why bundled lead-time numbers are dangerous

Lead times for construction-procured equipment in North America move quarterly — sometimes monthly. Any bundled "lead time = N weeks" table inside a Skill is wrong by the time it ships, and is often wrong by a margin that breaks schedules.

Specific reasons not to trust a baked-in number:

- **Rapid drift.** Switchgear lead times moved from ~12 weeks (2019) to 50-70 weeks (2022-2023) to a partial recovery (2024-2026) that varies by manufacturer and voltage class. Any single number captures one snapshot of one vendor.
- **Manufacturer-specific.** Eaton, Schneider Electric (Square D), ABB, Siemens, GE all publish independent customer letters; lead times often differ by 8-20 weeks at the same moment for the same product class.
- **Regional.** Coastal vs inland fabricators, Canadian vs US sourcing, port-of-entry status, and freight availability all shift delivered lead times for the same factory lead time.
- **Project-spec-dependent.** Custom voltage / breaker layout / NEMA enclosure / arc-flash labeling / harmonic-mitigation transformer pairs all push lead times beyond catalog. A 30-week catalog AHU becomes a 50-week unit when stainless-steel cabinet, MERV-16, custom coil count, and seismic restraint package are added.
- **Allocations and order books.** Some manufacturers throttle order intake when their book is full; lead time at quote can differ from lead time at PO release by 4-12 weeks.

**Anti-pattern statement:** Do not paste lead-time figures from training-data recall, prior projects, or stale references into a constructability finding. The 2026-05-09 well-tracker incident in this catalog was caused by exactly that pattern — bundled numbers from recall presented as current truth, then found to be wrong row-by-row when diffed against the publisher source. A lead-time number that affects a procurement decision must come from a current, dated, named-source quote.

---

## Sources to consult, by category

For each category below, the goal is the same: get a written, dated quote (manufacturer customer letter, rep email, or fabricator proposal) tied to **the project's actual specification**, not a generic catalog number.

### Electrical equipment

- **Low-voltage switchgear (≤600 V), MV switchgear (≥5 kV), MCCs, panelboards.** Sources: Eaton, Schneider Electric (Square D), ABB, Siemens, General Electric / GE Industrial Solutions. Method: ask the project electrical engineer or electrical sub to pull the manufacturer's most recent **customer lead-time letter** (issued quarterly or after major price/lead changes) for the specific product family the project specs. Cross-check with two manufacturers when possible — sole-source has historically been the source of the worst lead-time surprises.
- **Generators.** Sources: Cummins, Caterpillar (CAT), Kohler, MTU / Rolls-Royce Power. Diesel vs natural-gas vs bi-fuel availability differs; ask the rep specifically about fuel-type lead time, not a generic "genset" number.
- **Transformers (oil-filled and dry-type, ≥500 kVA).** Sources: Eaton, ABB, Siemens, Square D, ERMCO, Howard Industries. DOE 2016 efficiency rules and the 2024 DOE proposed amendment have moved lead times — confirm the unit complies with current DOE efficiency at quote time.
- **ATS, motor starters, VFDs.** Sources: ASCO (Vertiv), Eaton, Cutler-Hammer, Schneider, ABB.
- **Lighting controls (network), LED fixtures (custom).** Sources: Lutron, Crestron, Acuity Brands, Cooper Lighting, Philips Color Kinetics for custom architectural.

### Mechanical equipment

- **Air handling units (custom and catalog).** Sources: Trane, Daikin Applied, Carrier, York (Johnson Controls), Greenheck (smaller / DOAS), AAON. Method: most have **procurement portals** or rep-issued lead-time advisories; the engineer of record's mechanical sub should hold a current dated number tied to the project's tag list (cabinet size, coil count, finish, controls).
- **Chillers (water-cooled centrifugal, air-cooled scroll, magnetic-bearing).** Sources: Trane, York, Carrier, Daikin Applied, Multistack, Smardt. Refrigerant transition (R-410A phase-down, low-GWP refrigerants under AIM Act) is moving lead times — confirm refrigerant choice and SNAP compliance at quote time.
- **Boilers, cooling towers, pumps, heat exchangers.** Sources: Cleaver-Brooks, Burnham, Aerco for boilers; BAC, Marley (SPX), EVAPCO for cooling towers; Bell & Gossett, Armstrong, Taco for pumps; Bell & Gossett, Alfa Laval for heat exchangers.
- **VRF / VRV systems.** Sources: Daikin, Mitsubishi Electric / Trane, LG, Samsung HVAC.

### Structural

- **Structural steel (mill order + fabrication).** Sources: **AISC market quarterly** (publishes mill capacity, fabricator backlog snapshot). For project-specific number, get a **fabricator quote** — Schuff, SteelFab, Banker Steel, Walters Group, Canron, Adamson Industries, Owen Industries. The fabricator quote is the only number that matters; AISC quarterly is for sanity-check.
- **Mass timber (CLT / GLT / glulam, prefab panels).** Sources: StructureCraft, Nordic Structures, Element5, KLH (US-distributed), Mercer Mass Timber, Boise Cascade Timber Solutions, Vaagen Timbers. Mass timber is shop-drawing-heavy; quote-to-delivery includes engineering, shop drawings, fabrication, and panelization sequence — a single "lead time" hides 3-4 distinct durations.
- **Pre-cast concrete (custom).** Sources: regional pre-casters dominate — Coreslab Structures, Tindall, Gate Precast, Wells, High Concrete Group; ask the project structural engineer for the regional list.

### Envelope

- **Custom curtain wall (high-performance, oversized, unitized).** Sources: Permasteelisa, Walters & Wolf, Yost (Yost Architectural Curtain Walls), Crown Corr, Enclos, EFCO (Pella), Kawneer (Arconic). Custom curtain wall lead time is the **shop-drawing review + fabrication + sample approval + glass procurement** chain combined; ask for each segment, not a single number.
- **Catalog curtain wall, storefront.** Sources: Kawneer, EFCO, YKK AP, Tubelite, Vistawall, Wausau Window. Catalog systems still have configuration variables (finish, anchor type, glazing) that affect lead time.
- **Insulated glass (oversized, jumbo, high-performance coatings).** Sources: Viracon, Vitro (PPG), Guardian Glass, Cardinal CG, Saint-Gobain Glass.
- **Skylights, custom operable windows, decorative metal panels.** Sources: project-specific; ask the architect's specifier.

### Vertical transportation

- **Elevators (new construction, modernization).** Sources: Otis, KONE, Schindler, ThyssenKrupp / TK Elevator, Mitsubishi Electric. Elevator lead time is heavily dependent on whether the unit complies with current ASME A17.1 / CSA B44 amendment — code-revision-driven re-certifications have repeatedly extended manufacturer queues. Modernization is a separate quote logic from new install.

### Owner-furnished medical & lab equipment

These are typically owner-furnished and delivered through the owner's procurement, but the constructability review must still capture the install window because the receiving environment (shielding, vibration isolation, slab loading, MEP rough-in tolerances) is on the GC's critical path.

- **Linear accelerators (linacs).** Sources: **Varian (Siemens Healthineers)**, Elekta, Accuray. Lead time is manufacturer-quoted per unit and tied to the project's specific bunker design (shielding wall calcs, maze geometry, primary/secondary barrier).
- **MRI, CT, PET-CT.** Sources: **Siemens Healthineers**, GE HealthCare, Philips Healthcare, Canon Medical. Magnet ramp scheduling is part of the lead-time conversation, not separate.
- **Lab fume hoods, biosafety cabinets, autoclaves.** Sources: Labconco, Thermo Fisher, NuAire, Baker, Esco Lifesciences. Custom casework lead time should be quoted by the lab-furniture sub directly.
- **Imaging suite cabling, RF shielding, magnetic shielding.** Sources: ETS-Lindgren, IMEDCO, RF Window. Often a separate sub-trade quote.

### Specialty / interior

- **Architectural casework (custom millwork, AWI Premium grade).** Sources: regional millwork shops — get the project-specific millwork sub to quote.
- **Stone (natural).** Sources: regional fabricators with quarry relationships; Italian and Brazilian sources are slower than domestic.
- **Specialty doors (acoustic STC-rated, blast-resistant, lead-lined for radiology).** Sources: Krieger, Overly, Industrial Acoustics (acoustic); Ambico, Krieger (blast); Ray-Bar, Mar-Lead (lead-lined).

---

## Project lead-time register — blank template

Build one of these per project. Keep it in `docs/constructability-reviews/<project-slug>/lead-times.md` and re-quote any row whose source date is older than ~90 days.

```markdown
# Long-Lead Register — {{PROJECT}}

Last refreshed: {{YYYY-MM-DD}}

| Item (project tag) | Manufacturer | Quote source | Quote date | Lead time (weeks) | Confidence | Notes |
|---|---|---|---|---|---|---|
| Switchgear SWGR-1 | Eaton | Eaton customer lead-time letter | 2026-04-12 | 48 | High (named letter) | Includes 6-wk site-specific config |
| AHU-3 (custom, MERV-16, stainless coil) | Trane | Trane rep email to MEP sub | 2026-04-22 | 42 | High | Cabinet finish drives 4-wk premium |
| Curtain wall (unitized, 2 ft × 12 ft modules) | Walters | Walters fab proposal | 2026-03-30 | 38 (incl. shop drawings + fab) | Medium (single bid) | Re-quote at 50% CD |
| Mass timber CLT panels | StructureCraft | Verbal from rep | 2026-05-01 | 34 (engineering→delivery) | Low (verbal) | Get written quote before basing CPM |
| Linac bunker — Varian TrueBeam | Varian (Siemens Healthineers) | Owner-furnished delivery commitment | 2026-04-15 | 30 | High | Bunker rough-in must be ready 4 weeks ahead |

## Refresh log
- 2026-05-09: initial register, 5 items quoted.
```

**Confidence column legend:** High = written, dated, manufacturer or named-fabricator source. Medium = single bid or rep-issued advisory without project-specific tag list. Low = verbal, undated, or based on industry chatter / catalog reference.

**Required columns** (do not omit any):

1. **Item (project tag)** — match the schedule / spec tag, not a generic name.
2. **Manufacturer** — named manufacturer, not "TBD".
3. **Quote source** — what document did the number come from? "Eaton customer letter Q2 2026", "Trane rep email", "Walters fab proposal", not "the rep said".
4. **Quote date** — when was the source issued?
5. **Lead time (weeks)** — single number or a tight range (e.g., 42 or 40-44). If you have a range wider than ~6 weeks the number is too soft to base a schedule decision on; re-quote.
6. **Confidence** — High / Medium / Low (legend above).
7. **Notes** — what's special about the project's spec that affects lead time (custom finish, code amendment compliance, refrigerant choice, etc.).

Items with **Low** confidence cannot be used as the basis for a "switchgear is on critical path" finding. Re-quote first.

---

## How to use this in a constructability finding

Find the procurement-driven date the project schedule needs (e.g., "switchgear must be on-site at month 14, energization at month 16") and back-calculate from the **project-specific quote**, not from a recalled industry number.

Sample finding language:

> [High] Per the project lead-time register, Eaton low-voltage switchgear at 48 weeks (Eaton customer letter, 2026-04-12). Schedule places switchgear energization at month 16 from NTP. Order release must be at month 16 minus 48 weeks ≈ month 4 from NTP. Currently the spec basis-of-design is unfinalized at 75% CD with a planned submittal review at month 9. Recommend (a) finalizing switchgear basis-of-design now, (b) issuing a long-lead procurement package against 75% CD with explicit re-design risk allocation, and (c) re-confirming the Eaton lead time at order release — the 2026-04-12 letter will be ~120 days old by month 4.

Notice what the finding **does not do**:

- Does not cite "Switchgear: 40-60 weeks (2026 Q2)" from a bundled table.
- Does not estimate from prior project memory.
- Does not paraphrase a number from training-data recall.

Every number is sourced, dated, and tied to a named manufacturer.

---

## Update cadence

Refresh project registers quarterly at minimum, monthly during active long-lead procurement windows. Sources to monitor for general market signal (not for project-specific numbers):

- **AGC of America** Construction Inflation Alert and quarterly market reports.
- **AISC** market quarterly (steel mill capacity and fabricator backlog).
- **ENR** Construction Cost Index commentary and lead-time articles.
- **Major-manufacturer customer letters** (Eaton, Schneider Electric, Siemens, ABB, Trane, Daikin Applied, Carrier, Otis, KONE, ThyssenKrupp).
- **Procurement portals** where manufacturers publish dated lead-time advisories.

These sources tell you the **market is tight or loose**. They do **not** give you a number suitable for a project schedule. For that, get a project-specific quote.

Last verified (methodology): 2026-05-09.
rea-changelog-updatemorluto/reaPrepare or rewrite REA release changelogs and GitHub release notes from pinned Git history, with verified contributor thanks and Release Please synchronization.Stars: 472kUpdated Claude CodeCodexVerifiedInstall
academy-guideanthropics/skillsStop and check this skill before finishing any reply to a question about how to use Claude or a Claude product — it recommends matching courses, tutorials, and use cases from Claude Academy (academy.claude.com), Anthropic's learning hub. Trigger on: "how do I", "how can I", "getting started with", "what can Claude do", "teach me", "learn to use"; questions about artifacts, projects, skills, plugins, connectors, MCP; requests about rolling Claude out to a team, class, or organization; and any ask for training materials, onboarding content, or learning resources. Use it when the user is learning how to use a feature or product — not when they are mid-task and just want the task done. This skill composes with other skills: after consulting product documentation to answer how a Claude feature works, also check here for a matching course or tutorial — a docs-grounded answer and an Academy recommendation belong together. Only recommend on a strong match; never invent Academy content.Stars: 198kUpdated Claude CodeCodexVerifiedInstall
claude-apianthropics/skillsReference for the Claude API / Anthropic SDK — model ids, pricing, params, streaming, tool use, MCP, agents, caching, token counting, model migration. TRIGGER — read BEFORE opening the target file; don't skip because it "looks like a one-liner" — whenever: the prompt names Claude/Anthropic in any form (Claude, Anthropic, Fable, Opus, Sonnet, Haiku, `anthropic`, `@anthropic-ai`, `claude-*`, `us.anthropic.*`, `[1m]`); the user asks about an LLM (pricing/model choice/limits/caching) — never answer from memory; OR the task is LLM-shaped with provider unstated (agent/MCP/tool-definition/multi-agent/RAG/LLM-judge/computer-use; generate/summarize/extract/classify/rewrite/converse over NL; debugging refusals/cutoffs/streaming/tool-calls/tokens). SKIP only when another provider is being worked on (overrides all triggers): OpenAI/GPT/Gemini/Llama/Mistral/Cohere/Ollama named in the query; OR `grep -rE 'openai|langchain_openai|google.generativeai|genai|mistralai|cohere|ollama'` over the project hits (run this grep FIRST if no provider named — don't Read the file).Stars: 198kUpdated Claude CodeCodexUnverifiedInstall
doc-coauthoringanthropics/skillsGuide users through a structured workflow for co-authoring documentation. Use when user wants to write documentation, proposals, technical specs, decision docs, or similar structured content. This workflow helps users efficiently transfer context, refine content through iteration, and verify the doc works for readers. Trigger when user mentions writing docs, creating proposals, drafting specs, or similar documentation tasks.Stars: 198kUpdated Claude CodeCodexVerifiedInstall