DavidCho1999/archaiflow-skills / bundles/construction-admin/skills/constructability-review
constructability-review
VerifiedThis skill should be used when the user shares construction documents (DD set, 50%/100% CD, GMP set) and wants them reviewed through a constructor's lens — sequencing, tolerance stack-ups, MEP coordination, install access, lay-down logistics, temporary works, long-lead procurement, and phased operations. Trigger on 'constructability review', 'CM review', 'sequencing check', 'install access', 'crane reach', 'lay-down', 'long-lead', 'MEP coordination clearance', 'site logistics', or pasted CD context with build-feasibility intent. Generates a structured review markdown in `docs/constructability/` and appends to the project constructability index.
Constructability Review
Overview
Review a construction documents package against eight constructability axes — trade sequencing, tolerance stack, MEP coordination, install access & rigging, lay-down & site logistics, temporary works, materials procurement & lead times, and phased operations — and produce a written review that lives in docs/constructability/.
This is the CM-side / owner's-rep / preconstruction perspective. It catches the "looks fine on paper but cannot be built without rework" failures during DD or 50% CD, when redesign is still cheap. Aligned with NA practice: AGC of America constructability review checklists, CMAA preconstruction services scope, AIA Document G701 (Change Order) economics on what should-have-been-caught issues cost when caught later, and ASHRAE / ANSI / SMACNA installation tolerance standards.
Scope and limits — read first
What this does. Reads a document set the way a builder reads it, across
eight axes, and writes findings to docs/constructability/ with a severity tag
on each. A finding names the sheet or detail, the dimension, clearance, or lead
time in question, and what the fix costs now against what it costs in CA.
What this does not do.
- It does not carry lead times.
references/long_lead_items_2026.mdis a method for building a project-specific register out of dated vendor quotes, not a table to read a number from. Lead times move quarterly and differ by manufacturer, so the number in a finding is one you obtained and dated. - It does not carry assembly tolerances either. A tolerance finding cites AISC, ACI, SMACNA, or the manufacturer's installation guide, from your copy of it.
- It does not estimate cost. It shows where buildability drives cost; the CM or the cost consultant prices it.
- It does not check code compliance, set completeness, or design quality. Those
are
code-compliance-review,drawing-checklist, anddesign-critic. - It does not conclude that something cannot be built. Constructors find a way, and the review's job is to surface what that way costs.
What you need before starting. The set or the details in question, the delivery method and CD phase, the structural and envelope systems, and the site constraints. Current quoted lead times if procurement is one of the axes you want weighted.
When to use
Trigger on:
- Pasted CD set details, plan/section excerpts, RCP/MEP overlays, or schedule-and-logistics narratives with a constructability question.
- Project file paths to a CD set the user wants reviewed.
- Explicit asks: "constructability review", "can this be built", "sequencing check", "install access for the AHU", "MEP coordination clearance", "lay-down on this site".
- Hand-off from
bid-reviewwhen low bidder flagged a constructability concern in their qualifications.
Do NOT trigger for:
- Pure code/egress compliance (use
code-compliance-review). - Drawing-set completeness audit (use
drawing-checklist). - Submittal review during CA (use
submittal-review). - General design critique (use
design-critic). - Cost estimating (this skill flags constructability-driven cost risk; it does not produce independent estimates).
Workflow
Step 1 — Bootstrap if needed
Check that docs/constructability/index.md exists. If not:
python scripts/init_constructability_workspace.py
Step 2 — Anchor the project context
Constructability findings are project-specific. Pin context before applying axes.
- Read
docs/project.mdif it exists for delivery method (DBB, CMAR, DB, IPD), construction type (Type I-V per IBC), structural system (steel, CIP concrete, mass timber, hybrid), envelope system (curtain wall, panelized, brick veneer), site constraints (urban-infill, owner-occupied, weather-restricted), and CD phase (DD, 50% CD, 100% CD, GMP set). - Identify the dominant constructability risk category for the project: occupied-building renovation, urban high-rise lay-down constraint, mass-timber procurement, expedited fast-track, etc. The dominant risk drives axis weighting.
- Pull lead-time benchmarks from
references/long_lead_items_2026.mdfor current procurement realities (electrical switchgear, AHUs, custom glazing, elevators, structural steel deck).
Step 3 — Apply eight-axis review
Load references/constructability_axes.md for the full framework with sub-criteria. Quick reference:
- Trade sequencing & critical path — Is the implied sequence physically possible? Out-of-sequence work, predecessors blocked by later trades, unrealistic concurrent work in the same volume?
- Tolerance stack-up — Cumulative tolerance from structure to finish exceeds the detail's accommodation? Steel ±¼" + deck ±½" + topping ±⅛" + acoustic substrate ±⅛" can defeat a 1/8" reveal at the wall-to-floor joint.
- MEP coordination & rack space — Above-ceiling clear height accommodates duct + sprinkler + cable tray + lighting in real (not BIM-clashed-but-resolved) coordination? Riser stack alignment story-to-story? Shaft enclosure penetrations within rated-assembly limits?
- Install access & rigging — Crane / boom-truck reach for steel and pre-cast erection? Hoisting paths through future façade openings? Equipment-room dimensions for AHU / chiller / switchgear installation and future replacement (the "removal route" question)?
- Lay-down & site logistics — Material storage area on a constrained urban site? Truck deliveries through restricted streets? Crane swing radius respects neighbor airspace? Pedestrian protection per IBC §3306, OSHA 1926 Subpart M, and local DOB / DSA requirements?
- Temporary works — Shoring for excavation? Dewatering capacity vs. groundwater rate? Weather enclosure for winter concrete or interior finishes? Life-safety path during construction (egress paths, sprinkler activation, fire watch)?
- Materials procurement & lead times — Long-lead items (electrical switchgear 40-60 weeks 2026, AHU 30-50 weeks, custom curtain wall 24-40 weeks) ordered with lead-time buffer? Decisions for those items frozen at the schedule date that procurement requires?
- Phased operations & owner occupancy — If the building is occupied during construction (renovation, expansion, school during summer break), are temporary-condition floor plans coordinated with infection-control risk assessments (ICRA in healthcare), means of egress, mechanical of patient/student transitions (MOP), neighbor noise/vibration limits, and security boundaries?
Focus on the 3-5 axes with real signal for the project. An urban high-rise reads heavily on 4, 5, 6. A healthcare renovation reads heavily on 1, 7, 8. A suburban greenfield reads heavily on 2, 3, 7.
Step 4 — Write the review
Read assets/constructability-template.md, fill placeholders. Filename:
docs/constructability/<YYYY-MM-DD>-<slug>.md
Slug rule: lowercase, [^a-z0-9-] removed, max 40 chars, derived from project + CD phase or dominant risk (acme-hq-50pct, harbor-school-occupied-phasing). If a review with the same date+slug already exists, suffix -<n>.
Step 5 — Update the constructability index
python scripts/append_to_index.py \
--date 2026-05-09 \
--slug acme-hq-50pct \
--cd-phase "50%" \
--primary-axes "sequencing,mep-coordination,install-access" \
--severity-high 3
The script appends a row to docs/constructability/index.md. Do NOT edit the index manually with the Edit tool.
Step 6 — Report
Tell the user:
- Path to the review file.
- The 2-3 highest-severity findings (each with a recommended design move and an estimated change-order avoidance value when caught now vs at CA).
- Any long-lead items where the procurement decision is already late.
- Whether a follow-up
submittal-reviewchecklist should pre-load for the long-lead items called out.
Rules
- Every finding cites a specific drawing detail or sheet, plus the assembly tolerance / clearance / lead-time number being violated. "MEP coordination is tight" is not a finding; "AHU-3 corridor clear height of 8'-2" leaves 6" above 24" round duct + 8" lighting, no sprinkler reserve" is a finding.
- Severity tag each finding: High (will cause a change order or schedule slip if not addressed before CD), Medium (likely to surface as RFI in CA), Low (worth noting; resolvable without redesign).
- Lead-time claims cite a date source (RSMeans 2026 Q2, manufacturer's published lead time, prior project benchmark). Lead times have moved a lot since 2020; do not use pre-2023 numbers.
- Tolerance findings cite the contributing assemblies' tolerances and where they are sourced (AISC 303 for steel, ACI 117 for concrete, SMACNA for sheet metal, glazing manufacturer's installation guide).
- Phased-occupancy findings always reference the AHJ rule that drives the constraint (NYC DOB occupied-building protocols, CA HCAI for healthcare, school-district summer-only windows, GSA tenant-occupied protocols).
- Refuse to assert "this can't be built." If a detail is hard, the finding is "this drives the schedule / cost / coordination as follows" — constructors find a way; the review's job is to surface the cost.
Anti-patterns
- Reviewing every axis when only 3-4 carry the project's risk. Pick the dominant risk axis first and weight others against it.
- Generic findings ("coordinate MEP", "tight tolerance") without the specific detail / dimension / lead-time number. Useless to the design team.
- Treating BIM clash detection as constructability review. Clash detection is necessary, not sufficient — clearance for installation tools (the wrench arc, the crane hook, the lift table) is a separate analysis.
- Ignoring the temporary condition. Many projects have life-safety and egress that are compliant in the final state but non-compliant in mid-construction; that gap is a real risk.
- Out-of-date lead times. Switchgear at 12 weeks (2019 reality) vs 40-60 weeks (2026 reality) is the kind of error that derails a schedule.
- Editing
index.mdmanually instead of usingappend_to_index.py.
Resources
scripts/init_constructability_workspace.py— bootstrapdocs/constructability/and the constructability indexscripts/append_to_index.py— append a row todocs/constructability/index.mdreferences/constructability_axes.md— eight-axis framework with sub-criteria, NA tolerance / clearance / lead-time benchmarks, common failure modes, example findingsreferences/long_lead_items_2026.md— current (2026 Q2) lead-time table for switchgear, AHUs, chillers, custom curtain wall, structural steel, mass timber, elevators, with sourcing notesassets/constructability-template.md— review markdown template with severity-tagged findings block
Related skills
| Skill | Stars | Updated | Works with | Status | Install |
|---|---|---|---|---|---|
| rea-changelog-updatemorluto/reaPrepare or rewrite REA release changelogs and GitHub release notes from pinned Git history, with verified contributor thanks and Release Please synchronization. | Stars: 470k | Updated | Claude CodeCodex | Verified | Install |
| academy-guideanthropics/skillsStop and check this skill before finishing any reply to a question about how to use Claude or a Claude product — it recommends matching courses, tutorials, and use cases from Claude Academy (academy.claude.com), Anthropic's learning hub. Trigger on: "how do I", "how can I", "getting started with", "what can Claude do", "teach me", "learn to use"; questions about artifacts, projects, skills, plugins, connectors, MCP; requests about rolling Claude out to a team, class, or organization; and any ask for training materials, onboarding content, or learning resources. Use it when the user is learning how to use a feature or product — not when they are mid-task and just want the task done. This skill composes with other skills: after consulting product documentation to answer how a Claude feature works, also check here for a matching course or tutorial — a docs-grounded answer and an Academy recommendation belong together. Only recommend on a strong match; never invent Academy content. | Stars: 197k | Updated | Claude CodeCodex | Verified | Install |
| claude-apianthropics/skillsReference for the Claude API / Anthropic SDK — model ids, pricing, params, streaming, tool use, MCP, agents, caching, token counting, model migration. TRIGGER — read BEFORE opening the target file; don't skip because it "looks like a one-liner" — whenever: the prompt names Claude/Anthropic in any form (Claude, Anthropic, Fable, Opus, Sonnet, Haiku, `anthropic`, `@anthropic-ai`, `claude-*`, `us.anthropic.*`, `[1m]`); the user asks about an LLM (pricing/model choice/limits/caching) — never answer from memory; OR the task is LLM-shaped with provider unstated (agent/MCP/tool-definition/multi-agent/RAG/LLM-judge/computer-use; generate/summarize/extract/classify/rewrite/converse over NL; debugging refusals/cutoffs/streaming/tool-calls/tokens). SKIP only when another provider is being worked on (overrides all triggers): OpenAI/GPT/Gemini/Llama/Mistral/Cohere/Ollama named in the query; OR `grep -rE 'openai|langchain_openai|google.generativeai|genai|mistralai|cohere|ollama'` over the project hits (run this grep FIRST if no provider named — don't Read the file). | Stars: 197k | Updated | Claude CodeCodex | Unverified | Install |
| doc-coauthoringanthropics/skillsGuide users through a structured workflow for co-authoring documentation. Use when user wants to write documentation, proposals, technical specs, decision docs, or similar structured content. This workflow helps users efficiently transfer context, refine content through iteration, and verify the doc works for readers. Trigger when user mentions writing docs, creating proposals, drafting specs, or similar documentation tasks. | Stars: 197k | Updated | Claude CodeCodex | Verified | Install |