sprint-planner
VerifiedSprint Planner
Trigger
Activate on "plan sprint", "sprint planning", "what should we work on", "organize the backlog".
Behavior
Step 1: Get Input
Ask:
- Paste the backlog (titles, priorities, estimates)
- Team size
- Sprint duration (1 or 2 weeks)
- Any constraints or deadlines
Step 2: Plan
Sprint Goal (1 sentence)
Recommended Backlog | Item | Estimate | Priority | Dependencies | Owner |
Capacity Check
- Capacity: [X points/days]
- Planned: [total]
- Buffer (20%): [amount]
- Verdict: Over/Under/Right-sized
Stretch Goals (if team finishes early)
Risks to This Sprint
Example
Bad sprint plan (no capacity math, no priorities):
Sprint Goal: Work on stuff
Items: Auth, Dashboard, Bugs, API, Docs
Good sprint plan:
Sprint Goal: Ship auth migration to 100% of web users
Capacity: 3 engineers x 10 days = 30 eng-days. At 80% = 24 available.
| Item | Estimate | Priority | Dependencies | Owner |
|------|----------|----------|-------------|-------|
| Auth migration: 40% → 100% rollout | 8d | P0 | QA sign-off (due Mon) | Jake |
| Mobile session bug fix | 5d | P0 | Root cause analysis (done) | Sarah |
| Dashboard loading perf | 3d | P1 | None | Alex |
| API rate limit docs | 2d | P2 | None | Jake |
Planned: 18 eng-days | Buffer: 6 eng-days | Verdict: Right-sized
Stretch Goals:
- Begin Outlook calendar sync research (3d) — only if auth ships by Thursday
Risks:
- Mobile bug fix estimate is uncertain. If root cause is deeper than
diagnosed, it could take 8d instead of 5d. Mitigation: Jake pairs
with platform team. If not resolved by Wednesday, descope and carry
to next sprint.
Rules
- 80% capacity is the ceiling. Sprints loaded above 80% have a >50% chance of missing the goal.
- Flag items with unclear requirements. Unclear requirements are estimation landmines.
- Unresolved dependencies block sprint entry. Resolve before committing the item.
- Every item needs a definition of done.
Related skills
| Skill | Stars | Updated | Works with | Status | Install |
|---|---|---|---|---|---|
| slack-gif-creatoranthropics/skillsKnowledge and utilities for creating animated GIFs optimized for Slack. Provides constraints, validation tools, and animation concepts. Use when users request animated GIFs for Slack like "make me a GIF of X doing Y for Slack." | Stars: 197k | Updated | Claude CodeCodex | Verified | Install |
| ponytailDietrichGebert/ponytailLazy senior dev mode for any coding task: the smallest change that fully solves it, and a reply a busy human understands in one read. | Stars: 194k | Updated | Claude CodeCodex | Verified | Install |
| ponytail-debtDietrichGebert/ponytailHarvest every shortcut: comment into one debt ledger, so deferrals get tracked instead of forgotten. One-shot report. | Stars: 194k | Updated | Claude CodeCodex | Verified | Install |
| ponytail-debtDietrichGebert/ponytailList every `shortcut:` comment (and older `ponytail:` ones) as a debt ledger. One-shot report, changes nothing. Use for "ponytail debt", "what did ponytail defer", "list the shortcuts", /ponytail-debt. | Stars: 194k | Updated | Claude CodeCodex | Verified | Install |