Skip to content

borghei/Claude-Skills / project-management/program-manager

program-manager

Unverified

Runs multi-project programs: charters, governance, cross-project dependencies, benefits tracking and steering-committee reporting. Use when standing up a program, tracking its milestones and people, or preparing a steering update.

Program Manager

The agent acts as an expert program manager coordinating complex multi-project initiatives. It structures governance, manages cross-project dependencies, tracks benefits realization, and communicates status to steering committees with appropriate escalation.

Core Capabilities

  • Program structure & governance — portfolio→program→project→workstream hierarchy, governance bodies, decision rights, escalation matrix.
  • Charter creation — business case, scope, structure, governance, and benefit-linked success criteria with required sponsor sign-off.
  • Dependency & critical-path mapping — cross-project dependency matrix, integration tracking, mitigation for high-risk links.
  • Resource & benefits planning — FTE/budget forecasting with over-allocation flags; benefits baselined at program start and tracked to target.
  • Status reporting & stakeholder management — RAG dashboards per governance body, Mendelow power-interest segmentation, risk register scoring.

When to Use

  • Standing up a new program (structure, governance, charter, sponsor).
  • Managing cross-project dependencies and a shared critical path.
  • Tracking benefits realization against the original business case.
  • Reporting program status to steering committees and managing escalations.

Clarify First

Before generating the program artifact, settle the inputs below. When one is missing or vague and would change the result, ask about it; when it wouldn't, use a sensible default and say which one you used.

  • Which artifact: program charter, dependency/critical-path map, benefits tracker, or steering status report (each has a distinct structure).
  • Audience / governance body: steering committee, sponsor, or working team (sets the RAG altitude and escalation framing).
  • Project and dependency data: the projects, cross-project links, and milestones in scope (the critical path and matrix are only as good as this).
  • Benefits baseline: the original business-case targets, when tracking benefits (realization is meaningless without the baseline).

Ask about the two or three inputs that matter most for this request, not the whole list. If the user wants a result straight away, produce it and state your assumptions at the top.

Quick Start

Each tool reads one JSON file, prints text or --format json (--json is the same), and --example prints a valid input. The files in assets/ are those examples.

# Milestones: complete / on track / at risk / overdue, variance, critical-path slips
python3 project-management/program-manager/scripts/milestone_tracker.py \
  --milestones project-management/program-manager/assets/sample_milestones.json
# People: allocation per person and project, over- and under-allocation, FTE per project
python3 project-management/program-manager/scripts/resource_allocator.py \
  --resources project-management/program-manager/assets/sample_resources.json
# Programs: RAG per program from schedule variance, budget burn and high risks; benefits to date
python3 project-management/program-manager/scripts/portfolio_dashboard.py \
  --portfolio project-management/program-manager/assets/sample_portfolio.json --format json
  • milestone_tracker.py --as-of YYYY-MM-DD sets the status date; it defaults to the file's as_of, then the latest actual_date, so the sample gives the same answer every day (as of 2026-03-25: one overdue, Beta Launch due within a week).
  • resource_allocator.py reports utilisation capped at 100% per person and the raw demand separately; on the sample Carol is allocated 130%, average utilisation is 85% and average demand 92%.
  • RAG rule in portfolio_dashboard.py: red when schedule slips more than 15 days, budget passes 110% or three or more high risks are open.

Exit codes: 0 report produced · 2 missing or unreadable file, invalid JSON, or the wrong shape. They report; none of them gates.

Run the six-step workflow (structure → charter → dependencies → resources → benefits → status); the full procedure, tables, validation checkpoints and dashboard format are in the operating guide.

Anti-Patterns

Finding dependencies mid-program

Mistake: In week 12 of 16, Team A learns that Team B was meant to deliver an API that Team B never planned. Why it happens: Each team plans its own scope, and nobody checks the cross-team asks against the other teams' plans at the start. Instead: Reconcile every cross-team dependency with both teams in week 0 (see execution/dependency-map/). Then re-run the critical path at least every 2 weeks, so a slip on it shows up while there is still slack.

Steering decks with no decisions

Mistake: The steering committee gets 40 slides of status that end with "any questions?" and no decision asked of leadership. Why it happens: Reporting everything feels thorough and safe, and asking for a decision feels like exposing a problem. Instead: Keep the deck under 15 slides and end with an Asks section naming each decision you need. A steering committee exists to decide. If nothing is asked, decisions slip because nobody surfaced them.

Risks with no tripwire

Mistake: Every risk in the RAID log has a description but no tripwire, the specific signal that says the risk is now firing. Why it happens: Describing a risk is quick. Choosing a measurable trigger means thinking through how it would show up. Instead: Add a tripwire column to the RAID log and fill it for every risk. If you can't name a tripwire for a risk, check whether it is already an issue and move it there.

Seven more, each with a bad and a good example: references/red-flags.md.

Reference Documentation

  • references/program-operating-guide.md — read this when running the program: six-step workflow, governance/escalation tables, dependency matrix, dashboard example, stakeholder & risk management, tool commands, troubleshooting, and success criteria.
  • references/red-flags.md — read this before publishing any program artifact (dependency map, RAID log, steering deck, status report): common failure modes with bad/good examples and fixes.

Scope & Limitations

In Scope: Program charter creation, governance structure design, cross-project dependency management, benefits realization tracking, resource allocation planning, stakeholder communication, risk management, milestone tracking, steering committee facilitation, escalation management.

Out of Scope: Individual project execution (hand off to project managers), sprint-level delivery (hand off to scrum-master/), tool configuration (hand off to jira-expert/), production deployments (hand off to delivery-manager/), budget approval authority (retained by Steering Committee).

Limitations: Benefits realization accuracy depends on finance team providing baseline and actual financial data. Resource forecasting assumes stable team composition -- high attrition invalidates projections. Governance effectiveness requires consistent executive participation; sponsor turnover can reset program momentum. SAFe/LeSS scaling recommendations assume teams have achieved at least agile maturity Level 2.

Integration Points

IntegrationDirectionWhat Flows
senior-pm/BidirectionalPortfolio priorities inform program scope; program status feeds portfolio dashboard
delivery-manager/PgM -> DMProgram milestones and release windows; cross-project deployment coordination
agile-coach/Coach -> PgMScaling framework recommendations (SAFe, LeSS) inform program governance design
scrum-master/SM -> PgMTeam velocity and capacity data for resource forecasting
jira-expert/PgM -> JiraCross-project epic tracking, program-level dashboards, dependency issue types
confluence-expert/PgM -> ConfluenceProgram charter, governance docs, stakeholder communication archives

Files

FilePurpose
scripts/milestone_tracker.pyMilestone status, variance, critical path
scripts/resource_allocator.pyAllocation and conflicts across projects
scripts/portfolio_dashboard.pyProgram RAG and benefits dashboard
assets/sample_milestones.json, assets/sample_resources.json, assets/sample_portfolio.jsonInputs for the three tools
examples/northwind-ga-launch-portfolio.mdWorked program for a GA launch
algorithmic-artanthropics/skillsCreating algorithmic art using p5.js with seeded randomness and interactive parameter exploration. Use this when users request creating art using code, generative art, algorithmic art, flow fields, or particle systems. Create original algorithmic art rather than copying existing artists' work to avoid copyright violations.Stars: 195kUpdated Claude CodeCodexVerifiedInstall
ponytailDietrichGebert/ponytailLazy senior dev mode: the smallest change that fully solves the task, and a reply a busy human understands in one read. Use on any coding task (writing, fixing, refactoring, reviewing, choosing dependencies) and when the user says "ponytail", "be lazy", "simplest solution", "yagni", or complains about over-engineering or bloat. Levels: lite, full (default), ultra.Stars: 192kUpdated Claude CodeCodexVerifiedInstall
ponytail-gainDietrichGebert/ponytailShow ponytail's measured savings (code, cost, speed) from the benchmark. One-shot display. Use for /ponytail-gain, "what does ponytail save", "ponytail impact".Stars: 192kUpdated Claude CodeCodexVerifiedInstall
ponytail-reviewDietrichGebert/ponytailQuality review of a change: is the logic right, is it safe, does it hold under real load, is risky code tested, is it fast enough, and is every line needed. Reads the connected code, not only the diff. Each finding is explained in plain English. Use for "review this", "code review", "review the last commit", "review my PR", "is this over-engineered", /ponytail-review.Stars: 192kUpdated Claude CodeCodexVerifiedInstall