VerifiedRun a structured after-action review (postmortem, retrospective) on a launch, incident, or completed project to capture timeline, root cause analysis, contributing factors, and actionable lessons. Use this skill whenever the user wants to run a postmortem, retrospective, AAR, or after-action review on any past event. Triggers on after-action report, AAR, postmortem, retrospective, retro, post-incident review, what went well what didn't, lessons learned, blameless postmortem, root cause analysis, RCA, five whys. Also triggers when the user has just shipped something or just resolved an incident and wants to capture learnings.
| File | Kind | Size |
|---|---|---|
| README.md | markdown | 360 B |
| SKILL.md | skill md | 9.7 KB |
| references/aar-template.md | markdown | 8.1 KB |
references/aar-template.md
View on GitHub# AAR Template
Fillable after-action report template. Three variations: incident AAR, launch AAR, project closeout AAR. The structure is similar; the inputs and emphasis differ.
---
## Universal sections (used in all three variations)
### Header
```markdown
# AAR: [Event name]
**Type:** [Incident / Launch / Project]
**Date of event:** [YYYY-MM-DD or range]
**AAR date:** [YYYY-MM-DD]
**Severity / scope:** [SEV-1 / Major launch / Project closeout]
**Facilitator:** [Name]
**Participants:** [Names]
**Distribution:** [Internal only / Internal + customers / Public]
```
---
## Variation 1: Incident AAR
### Summary
> [2 to 3 paragraphs. What happened, what was the impact, what was the root cause, what are the top action items. Should stand alone for executives who read only this section.]
### Impact
- **Users affected:** [Number and segment. "All US users" or "Approximately 12% of paid customers in EU."]
- **Duration:** [Detection to resolution]
- **Severity:** [SEV-1 / 2 / 3 / 4]
- **Revenue impact:** [If quantifiable]
- **Customer-facing communication:** [What was said, when]
- **Regulatory implications:** [If any]
### Timeline
| Time | Event | Notes |
|---|---|---|
| T-X | [Pre-incident state, recent deploy, etc.] | |
| T-0 | [Detection event] | |
| T+5min | [Acknowledgment] | |
| T+10min | [Severity assessed, IC assigned] | |
| T+Xmin | [Investigation milestone] | |
| T+Ymin | [Mitigation applied] | |
| T+Zmin | [Verification] | |
| T+Nmin | [Resolution declared] | |
| T+Hours | [Customer comms, post-incident] | |
Timeline source: [Logs, chat, monitoring, IC notes]
### Detection
- **How was it detected?** [Alert / customer report / internal observation]
- **Time to detection:** [From event start to detection]
- **Was detection adequate?** [Should we have detected this faster? How?]
### Response
- **Time to acknowledgment:** [Detection to acknowledgment]
- **Time to mitigation:** [Detection to mitigation]
- **Time to resolution:** [Detection to resolution]
- **Were the right people involved?** [Yes / No, why]
- **Did the response procedure work?** [Yes / No, what gaps]
### Root cause analysis
**Surface symptom:** [What users experienced]
**Five whys:**
1. Why did [symptom] happen? [Answer]
2. Why did [Answer 1] happen? [Answer]
3. Why did [Answer 2] happen? [Answer]
4. Why did [Answer 3] happen? [Answer]
5. Why did [Answer 4] happen? [Answer - often the system fix]
**Or, causal chain (multiple contributing factors):**
- Factor 1 (technical): [Description]
- Factor 2 (configuration): [Description]
- Factor 3 (process): [Description]
- Factor 4 (monitoring): [Description]
### Contributing factors
What didn't cause this but made it worse, or removed safety nets:
- [Factor]
- [Factor]
- [Factor]
### What went well
- [Detection mechanism that worked]
- [Decision that was correct]
- [Tool that performed as designed]
- [Communication that was effective]
### Action items
| Action | Owner | Due | Type | Status |
|---|---|---|---|---|
| [Specific action] | [Name] | [Date] | Monitoring | Open |
| [Specific action] | [Name] | [Date] | Code | Open |
| [Specific action] | [Name] | [Date] | Process | Open |
| [Specific action] | [Name] | [Date] | Documentation | Open |
| [Specific action] | [Name] | [Date] | Training | Open |
### Lessons
[Reflections beyond the action items. Often the most-quoted section in the long term.]
---
## Variation 2: Launch AAR
### Summary
> [2 to 3 paragraphs. What launched, did it go well, what surprised us, what should we do differently next time.]
### Outcomes
- **What launched:** [Specific scope]
- **Launch window:** [Planned vs actual]
- **Maintenance time:** [If applicable]
- **Issues during launch:** [Count and severity]
- **Rollback?:** [Yes / No]
- **Post-launch incidents:** [In the first 7 days]
- **Business outcomes:** [If measurable, e.g., conversion impact]
### Timeline
| Time | Event | Notes |
|---|---|---|
| Pre-launch | [Major decisions, milestones] | |
| Launch start | | |
| Cutover steps | [Each step with timing] | |
| Verification | | |
| Public announcement | | |
| First 24 hours | [Notable observations] | |
| First week | [Notable observations] | |
### What went according to plan
- [Step that worked exactly as runbook described]
- [Communication that was clear]
- [Decision that proved correct]
### What deviated from plan
- [Deviation, why, what we did]
- [Deviation, why, what we did]
### What surprised us
- [Unexpected observation]
- [Unexpected user behavior]
- [Unexpected technical behavior]
### What we'd do differently
- [Change to runbook for next launch]
- [Change to pre-launch QA]
- [Change to communication plan]
### What we'd repeat
- [Practice that worked, want to keep]
### Action items
| Action | Owner | Due | Type | Status |
|---|---|---|---|---|
| [Specific action] | | | | |
### Lessons
[Reflections.]
---
## Variation 3: Project closeout AAR
### Summary
> [2 to 3 paragraphs. What we set out to do, what we delivered, what we learned, what comes next.]
### Goals vs outcomes
| Goal | Outcome | Notes |
|---|---|---|
| [Original goal 1] | [Met / Partially met / Not met] | [Notes] |
| [Original goal 2] | [Met / Partially met / Not met] | [Notes] |
| [Original goal 3] | [Met / Partially met / Not met] | [Notes] |
### Timeline
| Phase | Planned | Actual | Variance |
|---|---|---|---|
| Discovery | | | |
| Design | | | |
| Build | | | |
| QA | | | |
| Launch | | | |
### What went well
- [Practice / decision / process that worked]
- [Practice / decision / process that worked]
- [Practice / decision / process that worked]
### What didn't go well
- [Pain point with system-level explanation]
- [Pain point with system-level explanation]
### What surprised us
- [Surprising input from users / market / internal]
- [Surprising scale / complexity / opportunity]
### What we'd do differently
For people working on similar projects in the future:
- [Specific change]
- [Specific change]
- [Specific change]
### Decisions in retrospect
| Decision | Was it right? | Why or why not |
|---|---|---|
| [Major decision 1] | | |
| [Major decision 2] | | |
| [Major decision 3] | | |
### Action items
| Action | Owner | Due | Type | Status |
|---|---|---|---|---|
| [Specific action] | | | | |
### Lessons
[Reflections.]
### Recommendations for next phase
[If the project continues. Otherwise, recommendations for what builds on this work.]
---
## Universal facilitator guide
### Before the meeting (pre-work)
- Send the timeline draft to all participants
- Ask each participant to write their personal account of what they observed and did (1 to 2 paragraphs each)
- Compile contributing data: logs, metrics, ticket counts, customer feedback
- Send participants the agenda 24 hours in advance
### During the meeting
- Set the tone in the first 60 seconds: "This is blameless. Focus on systems, not individuals."
- Walk the timeline. Add corrections from participants.
- For root cause: ask "why" until the answers stop being substantive. Note when it shifts from technical to process.
- For action items: insist on specificity, owner, date.
- Don't let the meeting become a debugging session. Investigation happened before; this is for analysis.
- Capture the document live where possible. Edits in real time prevent recall errors.
### After the meeting
- Polish the document within 48 hours
- Distribute to broader audience
- File action items into a tracking system
- Schedule follow-up to verify action items closed (typically 30 days out)
---
## Common AAR anti-patterns
| Anti-pattern | What it looks like | Better |
|---|---|---|
| Naming and shaming | "Sarah deployed the bug" | "Our review process didn't catch the issue. Why? What checklist or test would have?" |
| Generic actions | "Improve testing" | "Add a test for X scenario to the existing test suite by [date]" |
| No follow-through | Action items filed, never tracked | Action item review at next AAR; pattern of unclosed items surfaces |
| Skipping success | Only failures discussed | Equal time to what went well |
| Sole authorship | One person writes the AAR | Group discussion + sole author for polish |
| Long delay | AAR happens 2 months later | AAR within 2 weeks of event |
| Skipping minor incidents | "Not worth the time" | Patterns hide in the minors |
Related skills
| Skill | Stars | Updated | Works with | Status | Install |
|---|---|---|---|---|---|
| reverse-engineer-anythingmorluto/reaReverse engineer native, managed, Electron/JavaScript, packaged, firmware, and browser targets with REA, and build agent environments (AgentEnv bundles) of web applications from a live instance or a capture, and of Linux desktop apps with a task from a request. Use shipped-artifact or requested runtime evidence to explain features, compare versions, decompile code, or guide a reconstruction. Skip REA for ordinary source-repository architecture analysis. | Stars: 472k | Updated | Claude CodeCodex | Verified | Install |
| diagnosing-superpowersobra/superpowersUse when a superpowers session went wrong and your human partner wants to know why — repeated work, ignored plans, stumbles, poor results, a skill that didn't fire, "it took too long", "why is it so expensive", "what is it doing" — or wants to build a bug report for the superpowers maintainers, for the current session or a past one identified by id or path, on any harness. | Stars: 322k | Updated | Claude CodeCodex | Verified | Install |
| dispatching-parallel-agentsobra/superpowersUse when facing 2+ independent tasks that can be worked on without shared state or sequential dependencies | Stars: 322k | Updated | Claude CodeCodex | Verified | Install |
| executing-plansobra/superpowersUse when executing an implementation plan in the current session as the implementer yourself — your human partner chose inline execution, or no subagent tool is available | Stars: 322k | Updated | Claude CodeCodex | Verified | Install |