name: sprint-plan
description: "Plan a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, selecting stories, or balancing sprint scope against velocity."
---
## Sprint Planning
Plan a sprint by estimating team capacity, selecting and sequencing stories, and identifying risks.
### Context
You are helping plan a sprint for **$ARGUMENTS**.
If the user provides files (backlogs, velocity data, team rosters, or previous sprint reports), read them first.
### Instructions
1. **Estimate team capacity**:
- Number of team members and their availability (PTO, meetings, on-call)
- Historical velocity (average story points per sprint from last 3 sprints)
- Capacity buffer: reserve 15-20% for unexpected work, bugs, and tech debt
- Calculate available capacity in story points or ideal hours
2. **Review and select stories**:
- Pull from the prioritized backlog (highest priority first)
- Verify each story meets the Definition of Ready (clear AC, estimated, no blockers)
- Flag stories that need refinement before committing
- Stop adding stories when capacity is reached
3. **Map dependencies**:
- Identify stories that depend on other stories or external teams
- Sequence dependent stories appropriately
- Flag external dependencies and owners
- Identify the critical path
4. **Identify risks and mitigations**:
- Stories with high uncertainty or complexity
- External dependencies that could slip
- Knowledge concentration (only one person can do it)
- Suggest mitigations for each risk
5. **Create the sprint plan summary**:
```
Sprint Goal: [One sentence describing what success looks like]
Duration: [2 weeks / 1 week / etc.]
Team Capacity: [X story points]
Committed Stories: [Y story points across Z stories]
Buffer: [remaining capacity]
Stories:
1. [Story title] — [points] — [owner] — [dependencies]
...
Risks:
- [Risk] → [Mitigation]
```
6. **Define the sprint goal**: A single, clear sentence that captures the sprint's primary value delivery.
Think step by step. Save as markdown.
---
### Further Reading
- [Product Owner vs Product Manager: What's the difference?](https://www.productcompass.pm/p/product-manager-vs-product-owner)
Related skills
| Skill | Stars | Updated | Works with | Status | Install |
|---|---|---|---|---|---|
| planning-and-task-breakdownaddyosmani/agent-skillsBreaks work into ordered tasks. Use when you have a spec or clear requirements and need to break work into implementable tasks. Use when a task feels too large to start, when you need to estimate scope, or when parallel work is possible. | Stars: 119k | Updated | Claude CodeCodex | Verified | Install |
| screenpipethedotmack/claude-memSearch screen and audio history recorded by Screenpipe and optionally save selected context into claude-mem. Use when the user asks to recall desktop activity, a meeting, or something seen in another app through Screenpipe. | Stars: 118k | Updated | Claude CodeCodex | Verified | Install |
| contact-widgetnexu-io/open-designSelf-contained floating chat widget with welcome screen, social links, meeting button, and message input. Single HTML file, zero dependencies. | Stars: 108k | Updated | Claude CodeCodex | Verified | Install |
| meeting-notesnexu-io/open-designMeeting notes page — title bar with attendees, agenda checklist, decisions block, action items table with owners + dates, and a "next meeting" footer. Use when the brief mentions "meeting notes", "minutes", "1:1 notes", "all-hands recap", or "会议纪要". | Stars: 108k | Updated | Claude CodeCodex | Verified | Install |