VerifiedSplits a spec into an ordered list of tasks, each with a single verifiable outcome, an assigned tier, and a delegation brief. Use when a spec exists but there is no plan, when work must be divided across agents or people, or when a task is too large to verify in one step. Produces a plan file, not code.
| File | Kind | Size |
|---|---|---|
| SKILL.md | skill md | 4.3 KB |
SKILL.md
View on GitHub---
name: work-breakdown
description: Splits a spec into an ordered list of tasks, each with a single verifiable outcome, an assigned tier, and a delegation brief. Use when a spec exists but there is no plan, when work must be divided across agents or people, or when a task is too large to verify in one step. Produces a plan file, not code.
license: MIT
metadata:
phase: plan
owners: [tech-lead]
version: "0.1.0"
---
# Work Breakdown
A plan is right when each task has one outcome you can check with one command, and the
order puts the riskiest thing first.
If there is no spec, use `spec-writing` first. Planning against unwritten requirements
produces a plan that changes every day.
## Process
1. **Read the repository before planning.** Existing patterns constrain the plan more than
preferences do. Note the conventions you found, with paths, and plan inside them or
state the deliberate deviation.
2. **Cut along seams that already exist.** A task spanning three modules is either three
tasks or one badly-drawn boundary. Prefer boundaries the code already has.
3. **Order by risk, not by ease.** The task that could invalidate the rest of the plan goes
first. If an unknown could do that, task one is a spike whose output is an answer, not
code you keep.
4. **Size to one verifiable outcome.** A task is right-sized when its definition of done is
a single command whose output you can read. Three commands means three tasks.
5. **Assign the lowest tier that clears the ceiling** (`references/escalation-ladder.md`).
Over-assignment hides a vague brief.
6. **Write a brief per task.** A task without one comes back wrong, and that is the
planner's defect.
7. **State dependencies explicitly.** Tasks with no dependency between them can run in
parallel, but two tasks that edit the same file are one task.
## Task format
```markdown
- [ ] **<id> · <title>** — `<agent>`
- Goal: <one sentence in observable behavior>
- Files in scope: <explicit paths>
- Pattern to follow: <path:line>
- Definition of done: `<the single command that must pass>`
- Out of scope: <what to leave alone>
- Stop condition: <what triggers an escalation>
- Depends on: <ids, or none>
```
## Sizing heuristics
| Symptom | Fix |
|---------|-----|
| The definition of done needs three commands | Split into three tasks |
| The task title contains "and" | Split at the "and" |
| You cannot name the files in scope | You do not understand it yet. Investigate first, as its own task. |
| The task touches more than one module | Either split, or the boundary is wrong |
| Estimating it feels impossible | It contains an unknown. Make removing that unknown task one. |
## Ordering
- Riskiest first. The purpose of order is to find out early that the plan is wrong.
- A task that unblocks several others outranks a task that unblocks none.
- Group tasks that touch the same file so they do not run in parallel.
- Prefer an order where each step leaves the system working. A plan with a broken middle
cannot be paused, and plans always get paused.
## Output
```markdown
## Plan: <feature>
### Sequence rationale
<which task removes the most risk, and why this order>
### Parallelisable
<which ids can run at once, and which must not share files>
### Tasks
<the task list>
### Not in this plan
<what was deliberately left out>
```
## Verification
- Every task has a definition of done that is a runnable command.
- Every task is assigned a tier, and the assignment clears that tier's ceiling.
- The dependency graph has no cycle.
- The first task is the riskiest, or the rationale says why not.
- No two parallel tasks edit the same file.
## Red flags
| Thought | Reality |
|---------|---------|
| "I'll do the easy tasks first for momentum" | You will discover the plan is wrong at the end instead of the start. |
| "This task is obvious, no brief needed" | Obvious to you. The brief is for whoever picks it up. |
| "I'll assign it senior to be safe" | Over-assignment is a symptom of a vague brief, not caution. |
| "The order does not matter much" | Order is the plan. If it did not matter you would not need one. |
| "I'll write this task myself, it is small" | Then it is a T0 task with a brief. Your output is the plan. |
| "We can plan the rest as we go" | Plan to the next verifiable milestone at least. Beyond that, say so explicitly. |
Related skills
| Skill | Stars | Updated | Works with | Status | Install |
|---|---|---|---|---|---|
| reverse-engineer-anythingmorluto/reaReverse engineer native, managed, Electron/JavaScript, packaged, firmware, and browser targets with REA, and build agent environments (AgentEnv bundles) of web applications from a live instance or a capture, and of Linux desktop apps with a task from a request. Use shipped-artifact or requested runtime evidence to explain features, compare versions, decompile code, or guide a reconstruction. Skip REA for ordinary source-repository architecture analysis. | Stars: 471k | Updated | Claude CodeCodex | Verified | Install |
| diagnosing-superpowersobra/superpowersUse when a superpowers session went wrong and your human partner wants to know why — repeated work, ignored plans, stumbles, poor results, a skill that didn't fire, "it took too long", "why is it so expensive", "what is it doing" — or wants to build a bug report for the superpowers maintainers, for the current session or a past one identified by id or path, on any harness. | Stars: 322k | Updated | Claude CodeCodex | Verified | Install |
| dispatching-parallel-agentsobra/superpowersUse when facing 2+ independent tasks that can be worked on without shared state or sequential dependencies | Stars: 322k | Updated | Claude CodeCodex | Verified | Install |
| executing-plansobra/superpowersUse when executing an implementation plan in the current session as the implementer yourself — your human partner chose inline execution, or no subagent tool is available | Stars: 322k | Updated | Claude CodeCodex | Verified | Install |