VerifiedBuild and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.
| File | Kind | Size |
|---|---|---|
| SKILL.md | skill md | 4.3 KB |
| agents/openai.yaml | config | 167 B |
SKILL.md
View on GitHub---
name: codexkit-risk-register
description: Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.
version: 1.0.0
category: infra
---
# Risk Register Manager
## Purpose
Systematically identify, assess, and manage project risks using a structured register with probability/impact scoring and defined response strategies.
## When to use
- project kick-off to establish the initial risk baseline
- sprint or milestone reviews to update and add emerging risks
- before major decisions to assess risk exposure
- when stakeholders request a risk assessment report
## When not to use
- live incident response or post-mortem analysis
- security vulnerability scanning (use security tools)
- personal task risk assessment
## Inputs
- project scope, objectives, and constraints
- project type (predictive / adaptive / hybrid)
- stakeholder list and their risk tolerance
- known assumptions and dependencies
- lessons learned from similar projects (if available)
## Procedure
1. **Identify risks** using multiple sources:
- Internal: technical complexity, resource gaps, schedule pressure, budget
- External: market shifts, regulatory changes, vendor reliability, geopolitical
- PMBOK 8 emphasis: sustainability risks (ESG, climate, social impact)
- Techniques: brainstorming, PESTLE analysis, Risk Breakdown Structure (RBS)
2. **Assess each risk** qualitatively:
- Probability: Very Low (0.1) / Low (0.3) / Medium (0.5) / High (0.7) / Very High (0.9)
- Impact: Very Low (0.05) / Low (0.1) / Medium (0.2) / High (0.4) / Very High (0.8)
- Risk Score = Probability × Impact
- Red zone (≥ 0.25): immediate response required
- Yellow zone: response plan needed
- Green zone: monitor only
3. **Define response strategy**:
- For threats: Avoid / Transfer / Mitigate / Accept (active or passive)
- For opportunities: Exploit / Share / Enhance / Accept
4. **Assign ownership** — every risk has one named owner.
5. **Track residual risk** — after response, re-score to verify reduction.
6. **SAFe integration** — for SAFe teams, use ROAM board:
- R = Resolved | O = Owned | A = Accepted | M = Mitigated
## Output
- risk register table: ID | Category | Description | Trigger | Probability | Impact | Score | Owner | Response Strategy | Residual Risk | Status
- risk heat map summary (red/yellow/green distribution)
- top 10 risks with detailed response plans
- escalation list for sponsor or steering committee
- risk trend over time (risk burn-down if tracked across sprints)
## Definition of done
- every identified risk has a probability, impact, and score
- every red/yellow risk has a named owner and defined response strategy
- residual risk is assessed for all mitigated risks
- register is reviewable by stakeholders
## Examples
- "Build an initial risk register for a 6-month ERP migration project."
- "Update the risk register after Sprint 5 — add 3 new risks we discovered."
- "We have 15 risks but no response plans. Help me define strategies for the top 10."
## Quality Criteria
- [ ] All dependencies and prerequisites are documented
- [ ] Changes are reversible or include a rollback plan
- [ ] Security implications are assessed for each configuration change
- [ ] Monitoring and alerting are defined for post-deployment validation
## Verification (4C)
| Check | Question |
|-------|----------|
| **Correctness** | Are all configurations, permissions, and dependencies accurate? |
| **Completeness** | Does the setup cover dev, staging, and prod environments as needed? |
| **Context-fit** | Is the solution proportional to the problem (not over/under-engineered)? |
| **Consequence** | If deployed as-is to production, what is the highest-risk failure mode? |
## Edge Cases
- **Target environment has pre-existing configuration** — Scan for conflicts before applying changes. Document what to preserve.
- **Permissions differ between environments** — Test in staging first. Document the minimum permissions required.
- **Third-party service is unavailable or deprecated** — Document fallback or alternative. Include health-check endpoints.
## Changelog
- v1.0.0 — Initial release
Related skills
| Skill | Stars | Updated | Works with | Status | Install |
|---|---|---|---|---|---|
| rea-analysis-optimizationmorluto/reaOptimize REA providers and shared analysis workflows for agent context, latency, CPU, and memory while preserving correctness and Evidence. Use for analysis bottlenecks and cache or query design; CI/test-suite optimization belongs to rea-ci-tests-audit. | Stars: 470k | Updated | Claude CodeCodex | Verified | Install |
| rea-ci-tests-auditmorluto/reaAudit REA CI and test suites for correctness, fixture drift, false passes, and measured performance; use for suite or workflow investigations and efficiency changes, rather than ordinary feature testing or a single test failure. | Stars: 470k | Updated | Claude CodeCodex | Verified | Install |
| rea-tool-designmorluto/reaAudit, investigate, design, or change REA investigation tools, CLI/MCP contracts, provider capabilities, and Evidence semantics. | Stars: 470k | Updated | Claude CodeCodex | Verified | Install |
| ponytail-auditDietrichGebert/ponytailQuality audit of the whole repo: bugs, security, real load, missing tests, speed, and what to delete. Most important first. | Stars: 194k | Updated | Claude CodeCodex | Verified | Install |