Calculate and interpret Earned Value Management (EVM) metrics per PMBOK 8 Measurement Performance Domain. Compute SPI, CPI, EAC, ETC, TCPI, and generate variance narratives with corrective action recommendations. Use during project execution to assess schedule and cost performance.

FileKindSize
SKILL.mdskill md5.0 KB
agents/openai.yamlconfig186 B
---
name: codexkit-pmbok8-earned-value
description: Calculate and interpret Earned Value Management (EVM) metrics per PMBOK 8 Measurement Performance Domain. Compute SPI, CPI, EAC, ETC, TCPI, and generate variance narratives with corrective action recommendations. Use during project execution to assess schedule and cost performance.
version: 1.0.0
category: data
---

# Earned Value Management Analyst

## When to Use

- During project execution when tracking schedule and cost performance
- At monthly or sprint-end status reporting cycles
- When stakeholders need objective performance data beyond percentage-complete guesses
- When forecasting final project cost (EAC) using multiple methods

## Procedure

### Step 1 — Collect Baseline Data

1. Confirm Budget at Completion (BAC)
2. Record Planned Value (PV) at the reporting date
3. Record Earned Value (EV) — value of work actually completed
4. Record Actual Cost (AC) — money spent to date

### Step 2 — Calculate Core Metrics

| Metric | Formula | Interpretation |
|--------|---------|----------------|
| **SV** | EV − PV | < 0 = behind schedule |
| **CV** | EV − AC | < 0 = over budget |
| **SPI** | EV / PV | < 1.0 = behind schedule |
| **CPI** | EV / AC | < 1.0 = over budget |

### Step 3 — Forecast Completion

| Method | Formula | When to Use |
|--------|---------|-------------|
| **EAC (typical)** | BAC / CPI | Current CPI trend continues |
| **EAC (atypical)** | AC + (BAC − EV) | Variance was one-time |
| **EAC (SPI×CPI)** | AC + (BAC − EV) / (CPI × SPI) | Both schedule and cost pressure |
| **ETC** | EAC − AC | Remaining spend |
| **TCPI (BAC)** | (BAC − EV) / (BAC − AC) | Efficiency needed to hit BAC |
| **TCPI (EAC)** | (BAC − EV) / (EAC − AC) | Efficiency needed to hit new EAC |
| **VAC** | BAC − EAC | Forecast variance at completion |

### Step 4 — Generate Narrative

1. Summarize performance in plain language (ahead/behind, over/under)
2. Apply traffic-light rating: SPI/CPI ≥ 0.95 = 🟢, 0.8–0.94 = 🟡, < 0.8 = 🔴
3. Recommend corrective actions for any metric in 🟡 or 🔴 zone
4. Note trends by comparing with previous period metrics

## Inputs

| Input | Required | Format |
|-------|----------|--------|
| BAC (total budget) | Yes | Currency amount |
| PV (planned value to date) | Yes | Currency amount |
| EV (earned value to date) | Yes | Currency amount |
| AC (actual cost to date) | Yes | Currency amount |
| Prior period SPI/CPI | Recommended | Decimal (for trend) |

## Output

```markdown
## EVM Status Report — [Project Name] — Period [X]

### Performance Summary

| Metric | Value | Status |
|--------|-------|--------|
| BAC | $500,000 | — |
| PV | $200,000 | — |
| EV | $180,000 | — |
| AC | $210,000 | — |
| SV | -$20,000 | 🟡 Behind schedule |
| CV | -$30,000 | 🔴 Over budget |
| SPI | 0.90 | 🟡 |
| CPI | 0.86 | 🔴 |

### Forecast

| Method | EAC | VAC |
|--------|-----|-----|
| Typical (CPI trend) | $581,395 | -$81,395 |
| Atypical (one-time) | $530,000 | -$30,000 |
| SPI×CPI compound | $612,745 | -$112,745 |

### TCPI
- To hit BAC: **1.10** (achievable with corrective action)
- To hit EAC: **0.86** (current pace)

### Corrective Actions
1. CPI 🔴: Review scope for non-essential deliverables to reduce remaining cost
2. SPI 🟡: Fast-track critical path activities in next 2 sprints
3. Escalate to sponsor if CPI does not improve to 0.95 by Period X+2
```

## Definition of Done

- [ ] All 7 EVM metrics calculated correctly
- [ ] At least 2 EAC methods presented
- [ ] Traffic-light status applied to SPI and CPI
- [ ] Corrective actions provided for any metric in 🟡 or 🔴
- [ ] Narrative is in plain language (not just formulas)

## Examples

### Prompt

```text
My project has BAC = $500,000. As of end of Month 4:
PV = $200,000, EV = $180,000, AC = $210,000.
Last month SPI was 0.93, CPI was 0.89.
Generate a full EVM report with forecasts and corrective actions.
```

## Quality Criteria

- [ ] Data sources and assumptions are explicitly stated
- [ ] Calculations are reproducible from provided inputs
- [ ] Visualizations or tables have clear labels, units, and time ranges
- [ ] Caveats and confidence levels are documented for estimates

## Verification (4C)

| Check | Question |
|-------|----------|
| **Correctness** | Are formulas, aggregations, and statistical methods applied correctly? |
| **Completeness** | Does the analysis cover all requested metrics and time ranges? |
| **Context-fit** | Are the chosen metrics relevant to the business question being answered? |
| **Consequence** | If this data were used for a decision today, what blind spots remain? |

## Edge Cases

- **Missing or incomplete data** — Document gaps and their potential impact on conclusions. Provide ranges instead of point estimates.
- **Outliers skewing results** — Report with and without outliers. Document the decision to include or exclude.
- **Changing data definitions mid-period** — Split analysis at the change boundary and note the schema difference.

## Changelog

- v1.0.0 — Initial release
reverse-engineer-anythingmorluto/reaReverse engineer native, managed, Electron/JavaScript, packaged, firmware, and browser targets with REA, and build agent environments (AgentEnv bundles) of web applications from a live instance or a capture, and of Linux desktop apps with a task from a request. Use shipped-artifact or requested runtime evidence to explain features, compare versions, decompile code, or guide a reconstruction. Skip REA for ordinary source-repository architecture analysis.Stars: 470kUpdated Claude CodeCodexVerifiedInstall
diagnosing-superpowersobra/superpowersUse when a superpowers session went wrong and your human partner wants to know why — repeated work, ignored plans, stumbles, poor results, a skill that didn't fire, "it took too long", "why is it so expensive", "what is it doing" — or wants to build a bug report for the superpowers maintainers, for the current session or a past one identified by id or path, on any harness.Stars: 322kUpdated Claude CodeCodexVerifiedInstall
dispatching-parallel-agentsobra/superpowersUse when facing 2+ independent tasks that can be worked on without shared state or sequential dependenciesStars: 322kUpdated Claude CodeCodexVerifiedInstall
executing-plansobra/superpowersUse when executing an implementation plan in the current session as the implementer yourself — your human partner chose inline execution, or no subagent tool is availableStars: 322kUpdated Claude CodeCodexVerifiedInstall