Checks construction drawings and specs for what's missing, cross-trade coordination conflicts and scope gaps, with PE judgment. Use for 'what's missing', 'check coordination', 'scope gap', or researching an RFI before answering it. Not for drafting RFIs (rfi-drafter), code research (code-researcher) or reviewing a submittal package (the user runs /construction:submittal-review).

references/scope-gaps.md

View on GitHub
# Scope Gap Detection

Flag when responsibility is not explicitly assigned at these boundaries.

## GC / Subcontractor Boundaries

| Work Item | Common Gap |
|---|---|
| Cutting & patching after MEP rough-in | Who patches drywall? Spec 01 73 00 often silent. |
| Backing & blocking | Often not specified at all. Who provides for Div 10 accessories? |
| Temporary protection of finished floors | Who protects during subsequent work? |
| Final cleaning in ductwork, hoistways, telecom rooms | Spec 01 74 00 rarely specifies. |

## MEP Boundaries

| Interface | Common Gap |
|---|---|
| Roof curbs | Who provides the curb — roofer, mech, or sheet metal? |
| Equipment pads | Who provides dimensions/locations to concrete sub? |
| Sleeves | Who installs? Who firestops after pipe/conduit? |
| Condensate drains | Mech provides to floor drain — but who provides the drain? |
| Electrical connections | Who provides disconnect? Where is final connection point? |
| Controls wiring | Mech controls sub or electrician for low-voltage? |
| Kitchen equipment rough-in | Owner often furnishes equipment — who provides utility rough-in? |
| PV system roof penetrations | Electrical contractor installs conduit; roofing contractor flashes — who coordinates the curb detail? |
| Building automation controls wiring | Low-voltage contractor vs. electrical contractor vs. mechanical contractor — spec often silent |

## Envelope Boundaries

| Interface | Common Gap |
|---|---|
| Sill pan flashing | Air barrier contractor or window installer? |
| Perimeter firesafing at CW | CW installer or firestopping sub? |
| Coping/counterflashing | Roofer or metal panel installer? |
| Air barrier patching | Who patches after window/door installation? |
| Perimeter sealant at windows | Sealant sub (Spec 07 92 00) or window installer? |
add-product-e2e-evalpaperclipai/paperclipAdd or extend a Paperclip full-stack runner E2E workflow, fixture, matcher, or report evidence path for local or Daytona execution.Stars: 115kUpdated Claude CodeCodexVerifiedInstall
add-runner-evalpaperclipai/paperclipAdd or extend a Paperclip Runner protocol evaluation definition, roster, assertion, or report fixture with provenance and narrow validation.Stars: 115kUpdated Claude CodeCodexVerifiedInstall
diagnose-why-work-stoppedpaperclipai/paperclipCompatibility entry point for failed, stalled, looping, or over-recovered Paperclip work. Use fix-failed-paperclip-run for the full diagnosis, regression, repair, real verification, and green-PR workflow; honor an explicitly requested diagnosis-only scope.Stars: 115kUpdated Claude CodeCodexVerifiedInstall
fix-failed-paperclip-runpaperclipai/paperclipDiagnose and fix failed, stuck, slow, or incorrectly blocked Paperclip tasks and runs. Use with a task/run URL or failure report to trace the root cause, prove a regression red then green, check second-order effects, verify the real workflow, and deliver a PR with passing checks.Stars: 115kUpdated Claude CodeCodexVerifiedInstall