dleerdefi/claude-code-construction / skills/bid-evaluator
bid-evaluator
VerifiedEvaluate tabulated subcontractor bids against specs and drawings — scope gap analysis, exclusion risk scoring, award recommendation. Triggers: 'evaluate bids', 'bid evaluation', 'lowest responsible bidder'.
| File | Kind | Size |
|---|---|---|
| SKILL.md | skill md | 11.9 KB |
| agents/openai.yaml | config | 286 B |
| references/buyout-domain.md | markdown | 5.3 KB |
| references/drawing-review.md | markdown | 3.6 KB |
| scripts/export_bid_evaluation.py | script | 17.4 KB |
| scripts/sample_input.json | config | 4.5 KB |
| scripts/shared.py | script | 554 B |
references/drawing-review.md
View on GitHub# Drawing Review Guide for Bid Evaluation
Loaded during Step 1b (Drawing Review). Use to identify scope items visible on drawings but not explicit in specs — these differentiate thorough bidders from those who only read specs.
## By Drawing Type
### Floor Plans (A-1.x)
- Room count and names → finish quantities
- Partition types at each wall → drywall scope, rated assemblies
- Door marks → hardware sets, frame types
- Casework/millwork symbols → Div 06/12 scope
- Equipment callouts → MEP coordination
- Floor finish transitions → transition strip scope
- Column grid intersections → structural scope reference
### Reflected Ceiling Plans (A-2.x)
- Ceiling types and heights per room
- Light fixture count and type → electrical scope
- Diffuser/grille count → HVAC scope
- Sprinkler head locations → fire suppression scope
- Speaker/strobe locations → fire alarm/AV scope
- Access panel locations → ceiling sub scope
- Soffits and bulkheads → framing scope
### Elevations (A-3.x, A-5.x)
- Material callouts on exterior → cladding scope
- Window/storefront count and size → glazing scope
- Control/expansion joint locations → sealant scope
- Signage locations → specialty scope
- Louver count → HVAC scope
### Details (A-3.x, A-6.x)
- Specific product callouts (manufacturer, model)
- Assembly layers (substrate, membrane, finish)
- Flashing conditions → sheet metal / roofing scope
- Sealant joint types and locations
- Blocking/backing requirements for mounted items
### Structural (S-series)
- Foundation type → concrete scope
- Steel connection types → fabrication scope
- Embed schedule → cast-in items before pour
- Slab depressions and thickened slabs → concrete scope
- Expansion joint locations → multiple trades affected
### MEP Plans (M/P/E-series)
- Equipment tags and counts → unit pricing verification
- Routing complexity (exposed vs. concealed, tight spaces)
- Fixture counts → plumbing scope
- Panel locations and circuit counts → electrical scope
- Ductwork sizes and routing → sheet metal scope
### Schedules (embedded or A-8.x/A-9.x)
- Door schedule: count by type, hardware sets, fire ratings
- Window schedule: count by type, size, glazing spec
- Finish schedule: materials by room → flooring/painting quantities
- Equipment schedule: size, capacity, utility requirements
## Drawing-Derived Scope Items
Items visible on drawings that specs may not quantify:
| Drawing Feature | Derived Scope |
|----------------|---------------|
| Corner count on plan | Corner guard quantity (Div 10) |
| Linear feet of base on plan | Base trim/cove base quantity (Div 09) |
| Fixture count on plumbing plan | Accessory count (soap, towel, TP — Div 10) |
| Equipment tags on mech plan | Disconnect count (Div 26) |
| Rated partition count | Firestopping scope (Div 07) |
| Slab depression count | Waterproofing/fill scope (Div 03/07) |
| Penetration count through rated walls | Firestop system count |
| Roof penetration count | Curb/flashing count (Div 07) |
| Elevator count | Recall wiring, sump pump, ventilation (Div 14/26/22) |
## Quantity Cross-Checks
Use drawing-derived quantities to sanity-check bid quantities:
- **Fixture count from plumbing plan** vs. bidder's fixture count
- **Door count from schedule** vs. hardware set count in bid
- **Room count from finish schedule** vs. painting/flooring SF
- **Equipment count from mech schedule** vs. electrical disconnect count
- **Rated wall LF from life safety plan** vs. firestopping bid
Significant discrepancies (>10%) suggest the bidder didn't review drawings thoroughly — flag as scope gap risk.
Related skills
| Skill | Stars | Updated | Works with | Status | Install |
|---|---|---|---|---|---|
| slack-gif-creatoranthropics/skillsKnowledge and utilities for creating animated GIFs optimized for Slack. Provides constraints, validation tools, and animation concepts. Use when users request animated GIFs for Slack like "make me a GIF of X doing Y for Slack." | Stars: 198k | Updated | Claude CodeCodex | Verified | Install |
| ponytailDietrichGebert/ponytailLazy senior dev mode for any coding task: the smallest change that fully solves it, and a reply a busy human understands in one read. | Stars: 194k | Updated | Claude CodeCodex | Verified | Install |
| ponytail-debtDietrichGebert/ponytailHarvest every shortcut: comment into one debt ledger, so deferrals get tracked instead of forgotten. One-shot report. | Stars: 194k | Updated | Claude CodeCodex | Verified | Install |
| ponytail-debtDietrichGebert/ponytailList every `shortcut:` comment (and older `ponytail:` ones) as a debt ledger. One-shot report, changes nothing. Use for "ponytail debt", "what did ponytail defer", "list the shortcuts", /ponytail-debt. | Stars: 194k | Updated | Claude CodeCodex | Verified | Install |