This skill should be used when the user needs a phase-specific drawing-set checklist for an architectural project — SD, DD, CD, or IFC. Trigger on 'make a checklist', 'drawing set review', 'CD checklist', 'DD set review', or pasted phase + project-type context. Generates a structured checklist markdown in `docs/checklists/` and updates the project checklist index.

references/phase_deliverables.md

View on GitHub
# Phase Deliverables

Reference for per-phase deliverable expectations. Phase percent-complete ranges below are common practice (typically aligned with AIA B101-2017 §3.2 / §3.3 / §3.4 / §3.5 phase descriptions, but the percent values themselves are office-convention not AIA-mandated). Sheet enumerations and level-of-detail lists are common-practice synthesis, not direct quotations of any published authority. Project contracts may override these — defer to contract language when present.

See `_provenance.md` for source authorities and verification status. Items marked `[verify B101-2017 §X.X]` need the exact section pin confirmed.

---

## SD — Schematic Design (~15-30% complete)

**Source:** Phase scope per AIA B101-2017 §3.2 (Schematic Design Phase Services). Percent-complete range (15-30%) is office convention — no AIA / NCS pin available. Typical-sheet list is common practice; verify against firm standards.

**Intent:** Establish the project concept, scale, massing, and key program relationships. Confirm zoning, code path, and site response.

**Typical sheets:**

- G-001 cover sheet (project name, address, team, sheet index)
- G-002 code summary (occupancy, construction type, allowable area, exiting strategy at concept level)
- A-001 site plan (massing footprint, setbacks, north arrow, property line)
- A-100 series floor plans (single-line walls, room names, no dimensions or schedules)
- A-200 series exterior elevations (massing, fenestration intent, material zones)
- A-300 series building sections (1-2 key sections, floor-to-floor heights)
- Optional: 3D massing views, key precedent references, concept narrative

**Level of detail:**

- Single-line walls
- Room names without numbers
- No door/window schedules, no wall types, no details
- Material intent only (no specs)
- Structural and MEP coordination is conceptual — note major moves only

**Owner deliverable:** narrative + drawings sufficient to confirm program, scale, and budget order-of-magnitude. _Source: AIA B101-2017 §3.2 generally describes SD-phase deliverables [verify B101-2017 §3.2.5 for explicit deliverable list]._

---

## DD — Design Development (~35-50% complete)

**Source:** Phase scope per AIA B101-2017 §3.3 (Design Development Phase Services). Percent-complete range (35-50%) is office convention — no AIA / NCS pin available. Typical-sheet list is common practice; sheet-series naming follows NCS v6 Module 2.

**Intent:** Resolve the project to the point where systems, materials, and dimensions are fixed. Outstanding items should be selection-level, not strategy-level.

**Typical sheets:**

- G-series: cover, sheet index, code summary, life safety plans (egress, occupancy load, travel distance)
- A-100 plans with double-line walls, dimensions to grid and major openings, room numbers
- A-200 RCPs with ceiling heights, lighting layout intent, soffits, bulkheads
- A-300 elevations with fenestration sized, material zones called out, key heights
- A-400 building sections with floor-to-floor, structural depth zones, ceiling plenum
- A-500 wall sections at typical conditions (exterior, foundation-to-roof)
- A-600 enlarged plans (stairs, restrooms, kitchens, vertical transportation)
- A-700 schedules — door, window, partition (preliminary)
- A-800 details — typical assemblies (no full detail set yet)

**Level of detail:**

- Double-line walls, partition types tagged
- Dimensions to grid, openings, and key features
- Door/window/finish schedules in preliminary form
- Wall types defined; details for typical conditions only
- Structural grid coordinated with architectural plans
- MEP chases, shafts, and major equipment locations coordinated

**Owner deliverable:** drawings + outline specs sufficient for cost estimate within ~10%. _Source: AIA B101-2017 §3.3 describes DD-phase scope [verify B101-2017 §3.3.2 / §3.3.3 for outline-spec language]; cost-estimate accuracy is office convention._

---

## CD — Construction Documents (100% biddable)

**Source:** Phase scope per AIA B101-2017 §3.4 (Construction Documents Phase Services). "100% biddable" is office convention; AIA does not assign a numeric percentage. Sheet enumerations follow NCS v6 Module 2 sheet-series naming.

**Intent:** Drawings + specs are complete enough for a contractor to bid and build without interpreting design intent.

**Typical sheets:**

- All DD sheet series, fully resolved
- Complete schedules: door, window, partition, finish, hardware, equipment
- Full detail set: typical and project-specific assemblies, all transitions, all penetrations
- Wall sections at every distinct condition
- Enlarged plans for every special area
- Exterior wall details cover every joint, transition, termination
- Interior elevations for every wet area, casework, and significant feature wall
- Roof plan with drainage, penetrations, equipment, parapet conditions
- Reflected ceiling plans coordinated with MEP

**Level of detail:**

- Every dimension required to build is shown
- Every callout (detail bubble, section cut, elevation tag) lands on a real referenced sheet
- Every schedule entry references a real type
- All wall types, partition types, door types, window types defined
- Specifications cross-reference correctly
- Structural and MEP fully coordinated — clash check resolved

**Owner deliverable:** biddable / permit-ready set. Specs issued. No "by others" or "TBD" without contractual reason. _Source: AIA B101-2017 §3.4 describes CD-phase scope [verify B101-2017 §3.4.1 / §3.4.2]; "permit-ready" qualifier and the "no TBD / by others" rule are office convention._

---

## IFC — Issued for Construction (100% issued)

**Source:** "Issued for Construction" is industry/office convention for the post-permit set delivered to the contractor for construction. AIA B101-2017 does not define an "IFC" phase by name; bidding/negotiation is §3.5 and construction phase services are §3.6. The IFC issue itself is administrative, not a B101 service phase. Revision/delta conventions follow NCS v6 Module 2 + AIA G-series administrative documents.

**Intent:** The set the contractor is building from. CD set + final addenda + bulletin revisions incorporated.

**Typical sheets:**

- All CD sheets at final revision
- Revision cloud + delta tag for every change since the prior issue
- Title block updated to "Issued for Construction" with date
- Sheet index updated to current revision

**Level of detail:**

- Same as CD, with every revision incorporated
- No outstanding RFIs that block construction
- No "VIF" (verify in field) callouts unless intentional and noted

**Owner deliverable:** the set bound into the construction contract. Any change after this is via RFI, ASI, or change order. _Source: post-issuance change mechanisms (RFI / ASI / change order) follow AIA A201-2017 General Conditions and AIA G-series forms (G701 Change Order, G710 Architect's Supplemental Instructions, G714 Construction Change Directive). [verify A201-2017 §7 for change-order machinery]._

---

## Quick reference

_Source for table values: percent-complete columns are office convention (not AIA-mandated); wall depiction / schedule / detail completeness rows are common-practice synthesis aligned with AIA B101-2017 §3.2-§3.4 phase scopes and NCS v6 Module 2 sheet conventions._


| Phase | % complete | Wall depiction | Schedules | Details |
|-------|-----------|----------------|-----------|---------|
| SD | 15-30% | single-line | none | none |
| DD | 35-50% | double-line + types | preliminary | typical only |
| CD | 100% biddable | full | complete | full set |
| IFC | 100% issued | full + revisions | complete + revisions | full set + revisions |
rea-changelog-updatemorluto/reaPrepare or rewrite REA release changelogs and GitHub release notes from pinned Git history, with verified contributor thanks and Release Please synchronization.Stars: 472kUpdated Claude CodeCodexVerifiedInstall
academy-guideanthropics/skillsStop and check this skill before finishing any reply to a question about how to use Claude or a Claude product — it recommends matching courses, tutorials, and use cases from Claude Academy (academy.claude.com), Anthropic's learning hub. Trigger on: "how do I", "how can I", "getting started with", "what can Claude do", "teach me", "learn to use"; questions about artifacts, projects, skills, plugins, connectors, MCP; requests about rolling Claude out to a team, class, or organization; and any ask for training materials, onboarding content, or learning resources. Use it when the user is learning how to use a feature or product — not when they are mid-task and just want the task done. This skill composes with other skills: after consulting product documentation to answer how a Claude feature works, also check here for a matching course or tutorial — a docs-grounded answer and an Academy recommendation belong together. Only recommend on a strong match; never invent Academy content.Stars: 198kUpdated Claude CodeCodexVerifiedInstall
claude-apianthropics/skillsReference for the Claude API / Anthropic SDK — model ids, pricing, params, streaming, tool use, MCP, agents, caching, token counting, model migration. TRIGGER — read BEFORE opening the target file; don't skip because it "looks like a one-liner" — whenever: the prompt names Claude/Anthropic in any form (Claude, Anthropic, Fable, Opus, Sonnet, Haiku, `anthropic`, `@anthropic-ai`, `claude-*`, `us.anthropic.*`, `[1m]`); the user asks about an LLM (pricing/model choice/limits/caching) — never answer from memory; OR the task is LLM-shaped with provider unstated (agent/MCP/tool-definition/multi-agent/RAG/LLM-judge/computer-use; generate/summarize/extract/classify/rewrite/converse over NL; debugging refusals/cutoffs/streaming/tool-calls/tokens). SKIP only when another provider is being worked on (overrides all triggers): OpenAI/GPT/Gemini/Llama/Mistral/Cohere/Ollama named in the query; OR `grep -rE 'openai|langchain_openai|google.generativeai|genai|mistralai|cohere|ollama'` over the project hits (run this grep FIRST if no provider named — don't Read the file).Stars: 198kUpdated Claude CodeCodexUnverifiedInstall
doc-coauthoringanthropics/skillsGuide users through a structured workflow for co-authoring documentation. Use when user wants to write documentation, proposals, technical specs, decision docs, or similar structured content. This workflow helps users efficiently transfer context, refine content through iteration, and verify the doc works for readers. Trigger when user mentions writing docs, creating proposals, drafting specs, or similar documentation tasks.Stars: 198kUpdated Claude CodeCodexVerifiedInstall