VerifiedBuild and audit the plan for one iteration: goal, real capacity, commit vs stretch, dependencies, risks and definition of done. Use when planning the next sprint or auditing a plan for a team that keeps missing its sprints.
| File | Kind | Size |
|---|---|---|
| SKILL.md | skill md | 7.7 KB |
| assets/sample_sprint_plan.json | config | 2.1 KB |
| assets/sample_sprint_plan_flawed.json | config | 2.1 KB |
| assets/sprint_plan_template.md | markdown | 2.2 KB |
| references/capacity-math.md | markdown | 6.3 KB |
| references/sprint-anti-patterns.md | markdown | 6.7 KB |
| scripts/sprint_planner.py | script | 10.7 KB |
references/capacity-math.md
View on GitHub# Sprint Capacity Math
## 1. Why capacity math matters
Most sprints miss because the team committed more than their real
capacity. The standard story-point + velocity model often hides:
- PTO (vacation, sick, parental)
- On-call rotation overhead
- Meeting overhead
- Interrupt + support tax
- New-hire ramp
- Cross-functional reviews
- Production incident response
A team that "did 50 points last sprint" probably did 50 points *given that
sprint's PTO and interrupts*. Tomorrow's sprint will be different.
## 2. The per-person formula
```
Raw hours = sprint days × hours/day
- PTO / holidays
- Meetings (recurring + ad-hoc)
- On-call hours (avg per sprint)
- Interrupt tax (support, Slack, drive-bys)
- Ramp (new-hire / new-area discount)
= Available hours
× Focus factor (0.6-0.75)
= Effective hours for sprint work
```
### Sprint days
- 1-week sprint: 5 days
- 2-week sprint: 10 days (most common)
- 3-week sprint: 15 days
### Hours per day
- 8 (standard)
- 7 (with 1-hour lunch)
- 6 (very conservative; accounts for breaks)
### Focus factor
- 0.5 — heavy interrupt environment (support engineer)
- 0.6-0.7 — most product engineers
- 0.7-0.8 — focused product team in flow
- 0.8+ — rare; isolated specialist work
Don't assume 1.0. Engineering doesn't happen in 8-hour pure flow.
## 3. Per-team aggregate
Sum across the team:
```
Engineer A: 36 effective hours
Engineer B: 28 effective hours (on-call this sprint)
Engineer C: 0 effective hours (parental leave)
Engineer D: 36 effective hours
Engineer E: 30 effective hours (3 days PTO)
EM (50% IC): 18 hours
---
Total: 148 effective hours = ~18.5 days of real work
```
This is your real capacity. Commit ≤ 80% of this.
## 4. Story point calibration
If you use story points, calibrate to hours:
| Story points | Approximate hours | Typical |
|--------------|-------------------|---------|
| 1 | 2-4 hours | Trivial change |
| 2 | 4-8 hours | Small feature |
| 3 | 1 day | Standard story |
| 5 | 2-3 days | Larger story |
| 8 | 4-5 days | Should split |
| 13 | 1+ weeks | Definitely split |
| 20+ | 2+ weeks | Epic; not a story |
Calibrate quarterly. Each team's points mean different things.
## 5. Velocity tracking
Track per sprint:
- Committed points
- Stretch points
- Actually delivered points
- Carried over
After 3-5 sprints, you have signal:
- Average velocity (delivered)
- Velocity stability (standard deviation)
- Commit vs deliver ratio
Use **average velocity × commit ratio** for next sprint's commit.
Example:
- Avg velocity: 40 points
- Commit ratio: 0.85 (commit 47, deliver 40)
- Next commit: 40 × 0.85 = ~34 points
This is more conservative than naive "commit avg." Most teams under-deliver.
## 6. Common capacity drains
### On-call
- 1-week rotation on a noisy service: 30%+ of week
- 1-week rotation on a quiet service: 5-10% of week
- Plan zero new work for on-call week
### Support tier
- "Support engineer this week" = 50%+ time
- Mid-sprint pull to support = unplanned hours lost
### New hire ramp
- Month 1: 25% productivity
- Month 2: 50%
- Month 3: 75%
- Month 6+: 100%
Plan for ramp; don't commit at full productivity.
### Meetings
- Standup: 15 min × 10 days = 2.5 hrs
- Sprint planning: 2 hrs / 2-week sprint = 0.4 hrs/day
- Retro: 1 hr / 2-week sprint
- 1:1s: 1-2 hrs / week
- Cross-functional: 1-3 hrs / week
- Total: typically 8-15 hrs / 2-week sprint per engineer
### Interrupts
- Slack questions: ~30 min / day = 5 hrs / sprint
- Drive-by reviews / pairings: 1-3 hrs / sprint
- Production triage: 0-10 hrs / sprint
- Customer escalations: 0-8 hrs / sprint
Together: 6-25 hrs / sprint depending on team role.
## 7. Capacity for non-feature work
Reserve capacity for:
- Tech debt (10-20%)
- Production support (5-15%)
- Code review for the team
- New-hire ramp
- Sprint planning + retro
These often aren't planned but happen anyway. Reserve or surprise.
## 8. Capacity by role
### Senior engineer
- 60-70% on feature work
- 20-30% on review / mentoring / pairing
- 10% on tech debt / improvement
### Mid-level engineer
- 80% on feature work
- 15% on review
- 5% on overhead
### Junior engineer
- 70% on feature work
- 30% on learning / asking / re-doing
### Engineering manager (50% IC)
- 30-50% on feature work
- 50-70% on people / meetings / planning
Match capacity expectations to role.
## 9. Quarter-level capacity
Roll up capacity across sprints:
```
6 sprints × team's avg sprint capacity (after PTO etc)
= quarter capacity
Allocate to:
- Run the business (50%): bugs, support, tech debt, OKR maintenance
- Grow the business (35%): feature roadmap
- Transform the business (15%): bigger bets, experiments
```
If you're allocating 100% to feature roadmap, you're going to miss
because run-the-business absorbed the rest.
## 10. Capacity for adjacent work
Don't forget:
- Code review (~30 min per PR; 5-10 PRs / sprint per engineer)
- Pairing / mentoring
- Design reviews
- Architecture decisions
- Hiring (interviews × number of loops)
- Conferences / learning
- Recognition + retention activities
Sum these; they're real hours.
## 11. Mid-sprint reality
A healthy sprint plan:
- Has 15-20% buffer (commit + stretch < 100%)
- Allows for unplanned production / support
- Has a "shut down stretch first" rule
- Has a "drop a commit, don't push past" rule
When unplanned work arrives:
1. Is it truly urgent? (production incident, exec ask)
2. If yes: descope stretch first
3. If still over capacity: descope a commit; communicate to stakeholders
4. If can't descope (committed externally): formal mid-sprint adjustment with PO
## 12. Common capacity mistakes
- Assuming 1.0 focus factor
- Not subtracting on-call hours
- Forgetting PTO
- Underestimating interrupts
- Counting EM at 100% IC
- Counting new hire at 100% productivity
- Counting "support tier" person at 100% on new work
- No buffer for unknowns
- Stuffing commits + stretch to 100%
## 13. Per-sprint plan template (capacity section)
```
Sprint: [name]
Dates: [start - end]
Team capacity:
- Alice: 40 hrs (no PTO)
- Bob: 28 hrs (on-call this sprint)
- Carol: 32 hrs (1 day PTO)
- Dave: 0 hrs (parental leave)
- Eve: 40 hrs
- Frank (EM): 18 hrs (50% IC)
Total: 158 hrs = ~20 person-days
Commitment target (80%): 126 hrs
Stretch (15%): 24 hrs
Reserve (5%): 8 hrs
Velocity over last 3 sprints: 40, 42, 38 pts = avg 40
Commit ratio: 0.85
Next commit: 34 pts (~120 hrs)
Stretch: 6 pts (~24 hrs)
```
Related skills
| Skill | Stars | Updated | Works with | Status | Install |
|---|---|---|---|---|---|
| rea-analysis-optimizationmorluto/reaOptimize REA providers and shared analysis workflows for agent context, latency, CPU, and memory while preserving correctness and Evidence. Use for analysis bottlenecks and cache or query design; CI/test-suite optimization belongs to rea-ci-tests-audit. | Stars: 472k | Updated | Claude CodeCodex | Verified | Install |
| rea-ci-tests-auditmorluto/reaAudit REA CI and test suites for correctness, fixture drift, false passes, and measured performance; use for suite or workflow investigations and efficiency changes, rather than ordinary feature testing or a single test failure. | Stars: 472k | Updated | Claude CodeCodex | Verified | Install |
| rea-tool-designmorluto/reaAudit, investigate, design, or change REA investigation tools, CLI/MCP contracts, provider capabilities, and Evidence semantics. | Stars: 472k | Updated | Claude CodeCodex | Verified | Install |
| ponytail-auditDietrichGebert/ponytailQuality audit of the whole repo: bugs, security, real load, missing tests, speed, and what to delete. Most important first. | Stars: 194k | Updated | Claude CodeCodex | Verified | Install |