# Release Process: Maturity, Planning, Change Management & DORA

Read this when assessing delivery maturity, building a release plan and exit criteria, evaluating change requests, or interpreting DORA metrics. Also contains the release-readiness worked example, the cross-skill integration map, the troubleshooting matrix, and success criteria — all moved verbatim from `SKILL.md`.

## 1. Assess Delivery Maturity

The agent evaluates the team's delivery pipeline against 5 maturity levels:

| Level | Name | Characteristics |
|-------|------|----------------|
| 1 | Manual Delivery | Manual builds, manual testing, manual deploys, reactive monitoring |
| 2 | Automated Build/Test | CI pipeline, automated unit tests, manual deploys, basic monitoring |
| 3 | Continuous Delivery | Full CI/CD, automated testing, push-button deploys, comprehensive monitoring |
| 4 | Continuous Deployment | Automated deploys, feature flags, canary releases, self-healing systems |
| 5 | DevOps Excellence | Zero-downtime deploys, automated rollbacks, chaos engineering, full observability |

**Validation checkpoint:** Identify current level and target level. Focus improvement efforts on one level at a time.

## 2. Plan Release

The agent creates a release plan covering:

1. **Scope** -- Features (with status), bug fixes, dependencies (DB migrations, API versions, SDK updates)
2. **Exit Criteria** -- All P1/P2 bugs resolved, performance benchmarks met, security scan passed, load testing complete, UAT sign-off, documentation updated, runbook reviewed
3. **Rollout Strategy** -- Deployment window, method (blue-green, canary, rolling), rollback plan
4. **Communication Plan** -- T-7 (scope finalized), T-1 (go/no-go), T-0 (release notes), T+1 (customer notification)

Check each exit criterion against the release record before the go/no-go meeting. The skill has no release-checker tool; the record below shows the expected format.

**Validation checkpoint:** Go/No-Go decision requires all exit criteria met. Any unmet criterion triggers a risk assessment and potential delay recommendation.

## 3. Evaluate Change Requests

| Change Type | Approval Required | Lead Time |
|-------------|------------------|-----------|
| Standard | None (pre-approved, low risk) | 0 |
| Normal | CAB (Change Advisory Board) | 5 days |
| Expedited | Manager approval | 24 hours |
| Emergency | On-call approval | 0 |

Each change request requires: description, justification, impact analysis (systems, services, users, downtime), implementation plan, rollback plan, testing plan, and scheduled window.

**Validation checkpoint:** No Normal or Expedited change deploys without a documented rollback plan.

## Example: Release Readiness Check

A readiness record, filled in by the delivery manager:

```text
Release Readiness: v2.5.0
=========================
Type: Minor Release (new features)
Target Date: January 25, 2024

Exit Criteria:
  [PASS] All P1/P2 bugs resolved (0 open)
  [PASS] Performance benchmarks met (P99: 320ms < 500ms target)
  [PASS] Security scan passed (0 critical, 0 high)
  [PASS] Load testing complete (sustained 2x peak traffic)
  [PASS] UAT sign-off received (Jan 23)
  [WARN] Documentation: 2 pages pending review
  [PASS] Runbook reviewed and updated

Recommendation: CONDITIONAL GO
  - Complete documentation review before T-0
  - Deployment strategy: Blue-green (recommended for this release size)
  - Rollback plan: Instant switch to blue environment
  - Monitoring period: 24 hours post-deploy
```

## DORA Metrics

DORA now defines five software delivery performance metrics, grouped as throughput and instability (as of September 2026, [dora.dev/guides/dora-metrics](https://dora.dev/guides/dora-metrics/)). The level values below are the 2024 report's cluster descriptions (2024 Accelerate State of DevOps Report, "Performance levels").

| Metric | Definition | Elite (2024) | High | Medium | Low |
|--------|-----------|--------------|------|--------|-----|
| Deployment Frequency | How often changes are deployed to production | On demand (multiple deploys per day) | Once per day to once per week | Once per week to once per month | Once per month to once every six months |
| Change Lead Time | Commit to version control to deployed in production | Less than one day | One day to one week | One week to one month | One month to six months |
| Change Fail Rate | Share of deployments that require immediate intervention | 5% | 20% | 10% | 40% |
| Failed Deployment Recovery Time (formerly MTTR) | Time to recover from a deployment that fails and needs immediate intervention | Less than one hour | Less than one day | Less than one day | One week to one month |
| Deployment Rework Rate | Share of deployments that are unplanned and made because of a production incident | No level benchmark published | | | |

Reading notes:

- The 2024 change fail rate values are not monotonic (High 20%, Medium 10%). `scripts/delivery_metrics_tracker.py` uses monotonic bands (5/10/20%) so a lower fail rate never scores worse, and treats recovery between one day and one week as Medium.
- "MTTR" is still common in tooling. The tracker reports `failed_deployment_recovery_time` and keeps `mttr` as a JSON alias.
- Rework rate is optional. Mark unplanned fix deploys with `"rework": true` in the input and the tracker reports the rate without classifying it.
- The 2025 DORA report ("State of AI-assisted Software Development") centres on seven team profiles from cluster analysis rather than leading with the Elite/High/Medium/Low levels, alongside the DORA AI Capabilities Model. Treat the 2024 levels as the latest published cut-offs, and use the profiles to diagnose *where* a team is constrained (throughput, instability, or well-being) rather than to rank teams.

Deployments themselves run through the team's own pipeline. This skill measures them: feed the deploy log to `python scripts/delivery_metrics_tracker.py --data deploys.json` for the DORA metrics above.

## Cross-Skill Integration

| Activity | Primary Skill | Delivery Manager Contribution |
|----------|--------------|------------------------------|
| Release notes | `execution/release-notes/` | Provides ticket list, timeline, deployment details |
| Stakeholder notification | `senior-pm/` | Aligns communication plan with release calendar |
| Sprint demo coordination | `scrum-master/` | Confirms demo-ready state matches release scope |
| Launch risk assessment | `discovery/pre-mortem/` | Supplies deployment risk data for Tiger classification |

## Troubleshooting

| Problem | Likely Cause | Resolution |
|---------|-------------|------------|
| Canary deployment shows elevated errors but feature works in staging | Environment parity gap -- staging lacks production data volume, traffic patterns, or third-party integrations | Improve staging fidelity; use traffic shadowing before canary; define canary success thresholds based on production baselines, not staging |
| Release go/no-go keeps getting deferred | Exit criteria too rigid or too many items flagged as blockers at the last moment | Separate "must-have" from "nice-to-have" criteria upfront; run readiness checks at T-7 and T-3 to surface issues early |
| Incident post-mortems produce action items that never get implemented | Actions lack owners, due dates, or priority relative to feature work | Assign every action to a named owner with a calendar date; reserve sprint capacity for reliability work; track post-mortem actions in a dedicated Jira board |
| Error budget burns through in the first week of the month | Single large incident or multiple small incidents compounding | Implement burn-rate alerting at 50% and 75% thresholds; auto-freeze non-critical deployments when burn rate exceeds 1.5x |
| Change requests bypass the CAB process | Emergency change pathway overused; teams lack awareness of change types | Audit emergency changes monthly; retrain teams on change classification; add automation to flag changes missing required approvals |
| DORA metrics stagnate despite tooling investment | Measuring deployment frequency without addressing batch size, or measuring failed deployment recovery time (MTTR) without improving observability | Focus on leading indicators (batch size, test coverage, observability depth) before expecting DORA improvement |
| Rollback takes longer than expected | Rollback plan not tested; database migrations are not backward-compatible | Require rollback rehearsal for every major release; enforce backward-compatible migration policy; blue-green with instant switch as default strategy |

## Success Criteria

- Change failure rate stays below 5% measured over a rolling 30-day window
- Failed deployment recovery time (formerly MTTR) for SEV-1/SEV-2 incidents is under 1 hour
- 100% of SEV-1/SEV-2 incidents produce a post-mortem with action items within 48 hours
- Error budget consumption stays below 80% in any given month
- Release cadence meets or exceeds the target deployment frequency (weekly or better)
- Zero deployments proceed without a documented rollback plan
- DORA metrics show quarter-over-quarter improvement across all four classified measures, with rework rate trending down where tracked
writing-skillsobra/superpowersUse when creating new skills, editing existing skills, or verifying skills work before deploymentStars: 322kUpdated Claude CodeCodexVerifiedInstall
xlsxanthropics/skillsUse this skill any time a spreadsheet file is the primary input or output. This means any task where the user wants to: open, read, edit, or fix an existing .xlsx, .xlsm, .xltx, .csv, or .tsv file (e.g., adding columns, computing formulas, formatting, charting, cleaning messy data); create a new spreadsheet from scratch or from other data sources; or convert between tabular file formats. Trigger especially when the user references a spreadsheet file by name or path — even casually (like "the xlsx in my downloads") — and wants something done to it or produced from it. Also trigger for cleaning or restructuring messy tabular data files (malformed rows, misplaced headers, junk data) into proper spreadsheets. The deliverable must be a spreadsheet file. Do NOT trigger when the primary deliverable is a Word document, HTML report, standalone Python script, database pipeline, or Google Sheets API integration, even if tabular data is involved.Stars: 198kUpdated Claude CodeCodexVerifiedInstall
shipping-and-launchaddyosmani/agent-skillsPrepares production launches. Use when preparing to deploy to production, or when asking what needs to be in place before shipping. Use when you need a pre-launch checklist, when setting up monitoring, when planning a staged rollout, or when you need a rollback strategy.Stars: 119kUpdated Claude CodeCodexVerifiedInstall
childhoodthedotmack/claude-memBabysit a shipped release after merge, publication, or deployment. Verify published packages, production behavior, installed plugins, and late CI or user reports until the observation window is clean; use babysit for PR readiness before release.Stars: 118kUpdated Claude CodeCodexVerifiedInstall